    Cleverly Solving the Problem of Ethylene "Heart" Installation——The Record of Research by Lu Min Team of China Huanqiu Sixth Construction

    • Last Update: 2022-01-08
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    "The'three units' are the stable operation of the ethylene plant.


    The "three units" of the ethylene plant refer to cracked gas compressors, ethylene compressors and propylene compressors


    At the site of the Guangdong Petrochemical Refining and Chemical Integration Project, the task of installing the "three units" of the ethylene plant fell on the shoulders of Lu Min's team


    In the foundation construction process of the "three units" of the ethylene plant, the treatment of the contact surface between the anchor bolts and the foundation is an indispensable and important process during the installation of the compressor unit, and it is also one of the important quality control points


    In the past, the control of the contact area between the anchor bolts and the foundation needed to be handled manually one by one, which required a huge investment in manpower, material and financial resources.


    To this end, the key team members set up a QC team to conduct special research on this issue


    “In the past, it was necessary to invest at least 10 people to handle the 157 anchor plate contact surfaces of the'three units', 4.


    This small tool was soon widely used in the compressor foundation construction process of ethylene, propylene and cracked gas projects, and won the national utility model patent certificate and the third prize of the China Petroleum Engineering Construction Association Excellent Quality Management Activity Achievement Award


    The problem of installing the basic tools was solved, and the problem of how to prevent oil leakage in the oil transportation system was placed in front of the team


    This is true


    The team began to set up the project again


    Not long ago, this technical transformation was successfully completed in the "three units" oil transportation of the ethylene unit of the Changqing Ethane to Ethylene Project.


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.