-
Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
China Paint Network
News: the effective progress of construction, is to measure a
deic paint
project good or bad important indicators, floor paint construction how to effectively control the progress?
(1) floor paint construction unit to submit the floor paint construction progress plan, by the owner or supervision unit after examination and confirmation.
(2) After determining the schedule of the floor paint project, it is necessary to prepare a large number of detailed supplementary plans to ensure its realization:
(1) week, monthly project construction implementation plan;
(2) material procurement plan;
(3) Division Engineering Construction Plan;
(4) sub-project construction plan;
(5) construction equipment deployment plan.
(3) check the progress of the floor paint project and compare the actual progress with the planned progress. Analyze the reasons for the delay (or advance) of the floor paint project and take timely remedial measures.
(4) revise the schedule. Throughout the construction process of the project, the preparation of revision schedules is often carried out many times. Usually the construction unit is not entitled to any additional funds for the revision of the schedule, as the failure of the construction unit to maintain a satisfactory construction schedule results in the modification of the plan. When the delay is not the responsibility of the construction unit, the extension is reasonable, but the owner is unwilling to postpone for various reasons, the floor paint construction unit will waive the extension claim and claim the cost claim. Because construction units in order to catch up with the original planned schedule, it is necessary to increase machinery, manpower, change the material procurement plan, or take other measures, these measures often have to increase the cost of the project. Therefore, when a reasonable extension is not approved and the plan is revised in accordance with the original completion target of the floor paint project, additional payment is granted.
When there are major changes or important events in the epoxy floor paint
coatings
project, such as the suspension of the project part, engineering accidents, increase or decrease the workload, change the design plan, change the construction plan, etc., will have a greater impact on the progress, and this kind of event makes the flooring paint project duration control become quite complex.
generally, construction units should adjust their schedules every once in a while, even if there are no significant delays. Because with the progress of the project, all kinds of floor paint construction conditions and environment are also changing, regular comprehensive inspection of the floor paint construction units themselves to strive for initiative, reduce costs, speed up the progress is very advantageous.
(5) The actual progress of the local floor paint project seriously deviated from the planned schedule, the completion period is difficult to complete the planned workload, the floor paint construction unit must immediately take measures to speed up the construction progress of the floor paint, if the form is not improved, it may be considered as a breach of contract, the contract will be terminated, the floor paint construction unit will be responsible for and compensate a series of losses.
Wuhan Fivans Building Materials Co. , Ltd. as a professional flooring enterprises, cost-effective products and professional construction team, in the construction process can effectively control the progress of construction, to create a customer satisfaction with the flooring products!