    The Biodegradable and Recyclable Center was informed that recently, Jiangyin Xingjia Plastics and Chemical Co.


    The Biodegradable and Recyclable Center was informed that recently, Jiangyin Xingjia Plastics and Chemical Co.


    basic situationbasic situation

    Project name: New degradable material project with an annual output of 40,000 tons

    Project name: New degradable material project with an annual output of 40,000 tons

    Construction unit: Jiangyin Xingjia Plastic Chemical Co.


    Construction unit: Jiangyin Xingjia Plastic Chemical Co.


    Construction Nature: Expansion

    Construction site: No.


    Construction site: No.


    Construction content and scale: Construction PBAT polymerization apparatus 1 sets biodegradable sheet production line 1 bar and the supporting utilities and auxiliary facilities, the purchase BDO storage and distribution system, a slurry system configuration, system esterification, precondensation system, Main equipment such as final polymerization system, pelletizing system, additive system, sheet production system, etc.


    Total investment: 140 million yuan, of which environmental protection investment is about 5 million yuan, accounting for 3.


    Construction period: The construction period of the project is 8 months.


    After completion, a production scale with an annual output of 40,000 tons of degradable new materials ( PBAT chips) will be formed .


    Process technology

    Process technologyProcess technology

    The project was undertaken by Prete and used the esterification-polymerization process for resin production.


    The project was undertaken by Prete and used the esterification-polymerization process for resin production.


    Reaction principle: Terephthalic acid ( PTA ) and adipic acid ( AA ) are esterified with 1,4- butanediol ( BDO ) at high temperature in the esterification kettle to produce butylene terephthalate ( BHBT ), 1,4- butanediol adipate ( BHBA );

    Under the action of high temperature esterification, BHBT and BHBA are polymerized to form polybutylene terephthalate ( PBT ) and poly -1,4- butane adipate ( PBA ), and finally form polybutylene terephthalate ( PBT ) through polycondensation.


    Under the action of high temperature esterification, BHBT and BHBA are polymerized to form polybutylene terephthalate ( PBT ) and poly -1,4- butane adipate ( PBA ), and finally form polybutylene terephthalate ( PBT ) through polycondensation.


    Table Table 1 1 project raw and auxiliary materials and energy consumption project raw and auxiliary materials and energy consumption

    Environmental protection

    Environmental protectionEnvironmental protection

    In addition, for the tetrahydrofuran wastewater generated during the PBAT production process , Jiangyin Xingjia Plastics and Jiangyin Biyue Sewage Treatment Co.


    In addition, for the tetrahydrofuran wastewater generated during the PBAT production process , Jiangyin Xingjia Plastics and Jiangyin Biyue Sewage Treatment Co.


    In February 2021, Sanfangxiang Group ( 600370 ) made public that its subsidiary Jiangyin Xingjia Plastic Chemical Co.
    , Ltd.
    plans to construct a PBAT project with an annual output of 120,000 tons .
    In addition to the above- mentioned project with an annual output of 40,000 tons of degradable new materials, the company will also invest 220 million yuan in the second phase of the 80,000 tons / year PBAT production line and supporting sheet production lines.

    Jiang Yin Xingjia Plastics Co.
    , Ltd.
    was established in 2002 Nian 6 Yue 21 days, Zhouzhuang Town, Jiangyin City address three bedrooms Xiangcun, mainly engaged in bottles with PET research and development, production and management, the company's main products are: non-fiber polyester chip, New functional materials and high-end functional sheets.
    Existing projects are located in Zhouzhuang Town, distributed in three plants: Nissan 400 tons of non fiber polyester chip project is located in a plant, the project in 2002 Nian 7 Yue 16 to obtain approval of the EIA Jiangyin City Administrative Bureau approved May 2007 Nian 7 Yue Passed the environmental protection inspection and acceptance of Jiangyin Environmental Protection Bureau (Zhouzhuang Branch) on the 9th , and is currently in normal production; the high-end functional sheet project with an annual output of 22,000 tons is located in Plant 2, and the project with an annual output of 30,000 tons of functional new materials is located in Plant 3.
    These two projects in 2020 Nian 9 Yue 7 date, obtains Wuxi City Bureau of administrative examination and approval of the EIA approval, is currently under construction.

    Jiang Yin Xingjia Plastics Co.
    , Ltd.
    was established in 2002 Nian 6 Yue 21 days, Zhouzhuang Town, Jiangyin City address three bedrooms Xiangcun, mainly engaged in bottles with PET research and development, production and management, the company's main products are: non-fiber polyester chip, New functional materials and high-end functional sheets.
    Existing projects are located in Zhouzhuang Town, distributed in three plants: Nissan 400 tons of non fiber polyester chip project is located in a plant, the project in 2002 Nian 7 Yue 16 to obtain approval of the EIA Jiangyin City Administrative Bureau approved May 2007 Nian 7 Yue Passed the environmental protection inspection and acceptance of Jiangyin Environmental Protection Bureau (Zhouzhuang Branch) on the 9th , and is currently in normal production; the high-end functional sheet project with an annual output of 22,000 tons is located in Plant 2, and the project with an annual output of 30,000 tons of functional new materials is located in Plant 3.
    These two projects in 2020 Nian 9 Yue 7 date, obtains Wuxi City Bureau of administrative examination and approval of the EIA approval, is currently under construction.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.