    Ministry of Ecology and Environment: 80% of projects do not need approval for environmental assessment, which will further improve approval efficiency

    • Last Update: 2021-07-03
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    "Global Coatings Network News"

    "Global Coatings Network News"



    According to data from the Ministry of Ecology and Environment, in the first half of this year, about 80% of the environmental impact assessments of my country's projects have implemented a filing system and no longer require approval.



    Cui Shuhong, Director of the Department of Environmental Impact Assessment of the Ministry of Ecology and Environment, introduced that the reform of "delegating management, delegating, managing, and servicing" EIA is one of the important contents of reforms in the field of ecological and environmental protection.



    He introduced that among the five administrative permits involved in the environmental impact assessment, three of the department's pre-examination, trial production approval, and completion acceptance permits have been cancelled according to law, and two are retained.



    Environmental impact assessment implements classified management, divided into reports, report forms and registration forms.



    At the same time, the time limit for EIA approval has also been greatly reduced, and supervision during and after the event has been strengthened.



    The reform of the environmental impact assessment system is one of the contents of the guidance issued this time.



    In terms of improving the efficiency of environmental review and approval, the opinions put forward to strengthen early guidance, proactively serve, and accept the implementation of major infrastructure, people's livelihood projects and major industrial layout projects immediately, that is, acceptance is evaluated, evaluation and review are synchronized, and green channels are opened to speed up processing.



    Will the reform of the environmental impact assessment system leave hidden dangers such as lax approval?




    In this regard, Cui Shuhong said that such concerns are unnecessary.
    He said that environmental impact assessment is no longer used as a project approval or approval condition, and the change from series approval to parallel approval is a major measure to optimize the approval system.
    This does not mean that projects that may have major environmental impacts can be started without environmental review approval.
    According to the law, construction projects that require EIA approval but have not undergone EIA approval shall not be started for construction, otherwise they shall be considered as "construction before approval".
    The legal penalties and the sanctions against related personnel are quite severe for the behavior of "building first without approval".

    In this regard, Cui Shuhong said that such concerns are unnecessary.
    He said that environmental impact assessment is no longer used as a project approval or approval condition, and the change from series approval to parallel approval is a major measure to optimize the approval system.
    This does not mean that projects that may have major environmental impacts can be started without environmental review approval.
    According to the law, construction projects that require EIA approval but have not undergone EIA approval shall not be started for construction, otherwise they shall be considered as "construction before approval".
    The legal penalties and the sanctions against related personnel are quite severe for the behavior of "building first without approval".




    "In the next step, we will continue to strengthen supervision during and after the event.
    " He said, one is to improve the supervision system, strengthen law enforcement, implement the main responsibility of enterprises, fully implement the pollution discharge permit system, and implement strict management and heavy penalties for "unapproved first construction" behaviors.
    ; Second, innovative regulatory technical ways and means, to detect illegal activities, the progressive realization of a comprehensive, real-time environmental regulation; third is to construct three is configured to build the whole society to participate in environmental regulatory system, the environmental protection of personal dishonesty, enterprise information into the integrity The "blacklist" is made public, and cross-departmental and cross-field joint punishments are implemented.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.