Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, 33 wind turbines in the second phase of the Ningxia Tongxin Xiaoluoshan Wind Farm project undertaken by the Fourth Bureau of Sinohydro successfully passed 250 hours of trial operation, achieving the goal of putting all the project into operation and making full preparations
for the wind farm to be transferred to formal commercial operation.
Ningxia Tongxin Xiaoluoshan Wind Farm Project is located near Hongcheng Water Village, Xiamaguan Town, Tongxin County, Ningxia Hui Autonomous Region, with a planned total wind farm area of about 40 square kilometers and a total installed capacity of 99 MW
.
A total of 66 1.
5 MW wind turbines were installed, supporting 1 110 kV booster station and 2 50 MW main transformers
.
It is equipped with 1 110 kV single return line, with a total length of 27.
1 km
.
The total length of 4 circuits of 35 kV collector lines in the field is 42 kilometers, and the road construction in the field is 42.
8 kilometers
.
In the early stage of trial operation, the project department organized all construction teams and equipment manufacturers to carefully check the installation quality and operation status of the fans, and actively used the windless weather to eliminate the collector lines and fans after shutdown, ensuring that all wind turbines were in good working condition
.
On May 8, 2016, 33 fans of the second phase of the project began 250 hours of trouble-free trial operation
.
During the trial operation, the operating wind turbine experienced an extreme wind speed of up to 22 meters per second, and the fan worked normally during the trial operation without any failure
.
By the morning of May 19, the cumulative power generation of the wind farm reached 7.
63 million kWh, and the trial operation was
successfully completed.
Recently, 33 wind turbines in the second phase of the Ningxia Tongxin Xiaoluoshan Wind Farm project undertaken by the Fourth Bureau of Sinohydro successfully passed 250 hours of trial operation, achieving the goal of putting all the project into operation and making full preparations
for the wind farm to be transferred to formal commercial operation.
Ningxia Tongxin Xiaoluoshan Wind Farm Project is located near Hongcheng Water Village, Xiamaguan Town, Tongxin County, Ningxia Hui Autonomous Region, with a planned total wind farm area of about 40 square kilometers and a total installed capacity of 99 MW
.
A total of 66 1.
5 MW wind turbines were installed, supporting 1 110 kV booster station and 2 50 MW main transformers
.
It is equipped with 1 110 kV single return line, with a total length of 27.
1 km
.
The total length of 4 circuits of 35 kV collector lines in the field is 42 kilometers, and the road construction in the field is 42.
8 kilometers
.
In the early stage of trial operation, the project department organized all construction teams and equipment manufacturers to carefully check the installation quality and operation status of the fans, and actively used the windless weather to eliminate the collector lines and fans after shutdown, ensuring that all wind turbines were in good working condition
.
On May 8, 2016, 33 fans of the second phase of the project began 250 hours of trouble-free trial operation
.
During the trial operation, the operating wind turbine experienced an extreme wind speed of up to 22 meters per second, and the fan worked normally during the trial operation without any failure
.
By the morning of May 19, the cumulative power generation of the wind farm reached 7.
63 million kWh, and the trial operation was
successfully completed.