echemi logo
Product
  • Product
  • Supplier
  • Inquiry
    Home > Chemicals Industry > China Chemical > PetroChina Tarim 600,000 tons/year ethane to ethylene project plans to be delivered by the end of June this year

    PetroChina Tarim 600,000 tons/year ethane to ethylene project plans to be delivered by the end of June this year

    • Last Update: 2021-11-24
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    According to reports, 1 month Tarim has been into the winter, shorter days and longer, the average daily temperature is below zero, heavy snow is cold, biting north wind, the temperature was in the fall to minus 20 degrees on the occasion, Beijing Huanqiu Company The construction site of the Tarim Ethane to Ethylene Project is still busy with traffic, machines roaring, hoisting operations, pipeline prefabrication, welding treatment, and steel erection.


    According to reports, 1 month Tarim has been into the winter, shorter days and longer, the average daily temperature is below zero, heavy snow is cold, biting north wind, the temperature was in the fall to minus 20 degrees on the occasion, Beijing Huanqiu Company The construction site of the Tarim Ethane to Ethylene Project is still busy with traffic, machines roaring, hoisting operations, pipeline prefabrication, welding treatment, and steel erection.


    Facing the first ray of sunshine in the winter morning every day, more than 3,000 builders were quickly busy on their work surfaces after accepting the daily safety announcements, and dozens of machinery and equipment were orderly with curved boom aerial vehicles, excavators, bulldozers and dozens of machinery and equipment.


    With the efforts of all parties, the main body of the main substation of the Tarim Ethane to Ethylene Project was capped 5 days in advance , the main body of the torch system was hoisted 3 days in advance, the main body of the ethylene cracking furnace was installed 20 days in advance , and the boiler low-temperature oven was ignited once.


    According to the editor of Chemical Online, this project is currently the largest single-investment refining and chemical project of PetroChina in southern Xinjiang.
    The main apparatus and facilities include annual ethylene 60 tons full density polyethylene 30 tons, high density polyethylene 30 million tons three process units and supporting public works and auxiliary production facilities.
    The ethylene plant adopts the ethane steam cracking process technology independently developed by PetroChina.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.