    On September 15, 2020, the key project in Shandong Province, Zibo Qixiang Tengda Chemical Co.
    , Ltd.
    , the first phase of the 100,000-ton/year MMA project was put into operation, and the 200,000-ton/year nitrile latex medical new material project was officially launched


    .


    The first phase of the MMA project was put into production as planned in September 2020, and qualified products were produced in 8 days and nights.
    The commissioning of this project means that Qixiang Tengda's new round of high-quality development has achieved a successful start


    .


    The first phase of the MMA project was put into production as planned in September 2020, and qualified products were produced in 8 days and nights.


    Product upgrades, moving towards a higher end of the value chain

    Product upgrade, moving towards a higher end of the value chain Product upgrade, moving towards a higher end of the value chain

    Qixiang started from carbon 4 deep processing.
    In 2016, it built a complete industrial chain, realized the "eat and squeeze" of carbon 4 resources, and became the largest carbon 4 deep processing base in China


    .


    Qixiang started from carbon 4 deep processing.


    MMA, also known as methyl methacrylate, can be used to produce plexiglass, high-grade paints, etc.


    The entire project construction includes: 200,000 tons/year MMA, 100,000 tons/year PMMA, 400,000 tons/year tert-butanol, etc.


    In 2018, the Qixiang Tengda MMA new material project was officially signed at the Confucian Business Conference, and in 2019, it was listed as a key project for the conversion of new and old kinetic energy in Shandong Province
    .


    In 2020, nitrile latex medical gloves are increasingly in short supply.


    In August 2020, the 200,000-ton/year nitrile latex project with a total investment of 680 million yuan and an area of ​​170 mu officially started
    .


    Carry forward the spirit of "Four Works" and "Four Days" to create a new speed of construction

    15 months to complete the installation: In June 2019, the project officially started construction


    .


    15 months to complete the installation: In June 2019, the project officially started construction
    .


    After more than 2,500 builders, more than 450 days and nights of hard work, hard work, skillful work, and hard work, it took 15 months to complete the two-year project, and a total of 5 reactors, 22 towers, and 97 heat exchange equipment were installed.
    There are 61 tanks, 211 pumps, 11 buildings and structures such as office buildings and control rooms, 3,132 meters of pipe galleries in the factory area and across the factory area, 30 spherical tanks, and 24 various liquid tanks

    .
    The entire project used a total of more than 40,000 tons of steel, equivalent to the total amount of steel used in Beijing's "Bird's Nest" stadium

    .

    In September 2020, the plant will be delivered as planned
    .
    Qixiang Tengda uses the strength of the whole company, carefully organizes, carefully deploys, fully guarantees transportation, cooperates closely, and is closely linked, and produces qualified products in 8 days and nights

    .

    In September 2020, the plant will be delivered as planned
    .
    Qixiang Tengda uses the strength of the whole company, carefully organizes, carefully deploys, fully guarantees transportation, cooperates closely, and is closely linked, and produces qualified products in 8 days and nights

    .

    The 200,000-ton/year nitrile latex project, Qixiang Tengda built and built on the sidelines, with time is money, efficiency is life's extraordinary determination and extraordinary measures, to promote the project construction, from start to production, it took 100 days to complete.
    The amount of work someone else can do in 240 days

    .
    The second phase project of 200,000 tons/year nitrile latex will also be completed and put into production as soon as possible

    .

    The 200,000-ton/year nitrile latex project, Qixiang Tengda built and built on the sidelines, with time is money, efficiency is life's extraordinary determination and extraordinary measures, to promote the project construction, from start to production, it took 100 days to complete.
    The amount of work someone else can do in 240 days

    .
    The second phase project of 200,000 tons/year nitrile latex will also be completed and put into production as soon as possible

    .

    Adhere to aggregation along the chain to achieve cluster development

    Adhere to along-chain aggregation to achieve cluster development Adhere to along-chain aggregation to achieve cluster development

    The MMA project produced qualified products, and the nitrile latex project was launched, marking that Qixiang Tengda has embarked on a golden track of great investment, great development, great output, and great progress
    .
    At the start-up ceremony of production, Che Chengju, chairman and general manager of Qixiang Tengda, proposed that by the end of 2021, five major projects and supporting projects of MMA, nitrile latex, propane dehydrogenation, propylene oxide and isononanol will be fully completed

    .

    The MMA project produced qualified products, and the nitrile latex project was launched, marking that Qixiang Tengda has embarked on a golden track of great investment, great development, great output, and great progress
    .
    At the start-up ceremony of production, Che Chengju, chairman and general manager of Qixiang Tengda, proposed that by the end of 2021, five major projects and supporting projects of MMA, nitrile latex, propane dehydrogenation, propylene oxide and isononanol will be fully completed

    .

    At the same time, make full use of the advantages of the capital market, introduce a modern enterprise system, build a high-end chemical new material industry platform with Qixiang Tengda as the core, and achieve cluster development together with upstream and downstream enterprises in the park
    .

    At the same time, make full use of the advantages of the capital market, introduce a modern enterprise system, build a high-end chemical new material industry platform with Qixiang Tengda as the core, and achieve cluster development together with upstream and downstream enterprises in the park
    .

    On the journey of building a 100 billion-level chemical new material industry cluster, Qi Xiang's development goals are becoming more and more clear, and the pace of progress is becoming more and more firm
    .
    Qixiang people will carry forward the Qixiang spirit of "unity and struggle, striving for the first-class", and adhere to the Qixiang philosophy of "doing the company's affairs as much as you do your own, and cherishing the company's money as you spend your own money", Efforts to run out of acceleration, strive to achieve new achievements, create a new highland for high-quality development, strive to be the standard-bearer benchmark for the transformation and upgrading of the traditional chemical industry, and make unremitting efforts for the economic development of the city and the happy life of the local people

    .

    On the journey of building a 100 billion-level chemical new material industry cluster, Qi Xiang's development goals are becoming more and more clear, and the pace of progress is becoming more and more firm
    .
    Qixiang people will carry forward the Qixiang spirit of "unity and struggle, striving for the first-class", and adhere to the Qixiang philosophy of "doing the company's affairs as much as you do your own, and cherishing the company's money as you spend your own money", Efforts to run out of acceleration, strive to achieve new achievements, create a new highland for high-quality development, strive to be the standard-bearer benchmark for the transformation and upgrading of the traditional chemical industry, and make unremitting efforts for the economic development of the city and the happy life of the local people

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.