    Shaanxi Coal Yulin Chemical "180 Project" is running at full capacity

    • Last Update: 2022-12-29
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On November 28, the 1.
    8 million tons/year ethylene glycol project of Yulin Chemical Company of Shaanxi Coal Group achieved full load operation
    .
    At present, the output of the three series of side-harvested polyester grade ethylene glycol has reached more than 75 tons per hour, and the daily output is more than
    5400 tons.

    Yulin Chemical implements the responsibility system of the members of the leadership team in the production and commissioning stage, and realizes the closed-loop management
    of arranging deployment, tracking and inspecting, and implementing sales items.
    Organize and convene special promotion meetings, seminars, mobilization meetings and regular process optimization meetings, etc.
    , study and judge the risks of the commissioning process, formulate process optimization measures according to the analysis of actual working conditions, balance the supply of materials throughout the plant, and effectively solve a series of problems
    。 At the same time, the company strictly controls the node plan, establishes a "3+2" test organization system, forms a three-level plan management mechanism, relies on the 15-minute rapid response of production and commissioning, daily inspection and assessment results and feedback and notification of management problems, and ensures the high-quality promotion of test runs and achieves the goal
    of full-load operation of the whole series through a series of measures such as expert special inspection, company-level PSSR, plant-wide interlocking, alarm, isolation, blind board hierarchical management, etc.

    It is reported that the first gasifier of the project was successfully put into feeding on September 8, and qualified polyester grade ethylene glycol products were produced on October 9, and the whole series of processes was opened
    on November 25.
    After the completion of the project, it will effectively reduce the foreign dependence of the domestic ethylene glycol market
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.