    Successful construction of drilling shale gas wells in Bohai Sea

    • Last Update: 2021-08-06
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Sinochem News Network News on July 3, PetroChina Bohai Drilling Second Cementing Company successfully completed the cementing construction of the Yang 101H88-1 well of the Sichuan shale gas project, setting a single well vertical in the Luzhou deep shale gas block.
    Records such as the deepest depth, the highest temperature at the bottom of the well, and the largest volume of cement paste
    .

    It is understood that the Yang 101H88-1 well has been drilled in four, with a depth of 6,265 meters, a maximum vertical depth of 4,320.
    43 meters, a maximum deviation of 97.
    21°, and a bottom hole temperature of 151.
    4°C.
    The geological conditions in the area are complex, the open hole section is prone to leakage, and the horizontal section is long It is difficult to center the casing, the wellbore is difficult to clean, the gas layer is widely distributed and active, and the cementing operation is difficult
    .

    Based on the principle of "one well, one policy" and "one section, one policy", the company established a research team, selected technical backbones to track the development of the well, and organized the construction party and related parties to jointly conduct a "consultation" on the well
    .


    The research team has demonstrated the cementing construction plan many times from the aspects of wellbore preparation, wellbore cleaning, flow resistance check, and lost circulation risk analysis, etc.


    At the same time, the company started the pre-construction production preparations ahead of schedule, and completed the on-site distribution of 18 vertical tanks, 280 tons of mixed and transported cement, and 140 cubic meters of cementing fluid within 3 days
    .


    During the on-site construction, the operators accurately controlled the various procedures and pressure parameters, and the on-site and design coincidence rate was 100%, and the construction task was successfully completed


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.