    1 Foreword
    Guangdong Institute of Finance North Campus basketball court renovation project, a total of 4 basketball courts need to be remodeled, the total construction area of 2652 square meters.
    2 Basic requirements
    2.1 basic requirements
    strength of building concrete C20 strength or more, flatness of 3m straight size error ≤3mm, there is a certain drainage slope (general horizontal ≤8, vertical ≤2 inches), concrete pouring must be water conservation not less than 7 days, the total maintenance period is not less than 28 days.
    2.2 cutting temperature seam
    after the new cement foundation pouring must cut a reasonable temperature telescopic seam, the principle is not greater than 6×10m for a square cutting, pouring construction plate between must cut temperature seam, temperature seam width of 5 to 8mm, seam depth of not less than 20mm, (150mm thick or more concrete foundation seam depth of not less than 30mm), to ensure that the base heat expansion cold shrink can be concentrated in the temperature seam changes, does not cause the foundation elsewhere cracking .
    2.3 acid wash
    to clean water wet the substate, with about 8% of the thin hydrochloric acid spilled and washed the substing, and then rinsed with clean water, and circled out the water accumulation, cleaning dry base should be free of white powder and float.
    2.4 temperature seam treatment
    after the foundation drying, with a special fill glue brushed on both sides of the temperature seam, and then compressible foam light squeeze temperature seam (reduce the base hot book cold shrink to the fill material squeeze deformation and affect the surface effect), exposing the base part with a hand grinder to level with the base surface, and then with fill glue brushed on the temperature seam surface, width of 8 0 to 100mm, thickness of 1.5mm, need to be divided into two brushes, (buffer base cold shrink when the silicon PU material coating force), laying a thin site (<3mm thick), the temperature seams on both sides of the substation (each 40 to 50mm) grinding down 1.5 to 2.0mm after filling treatment (to ensure smoothness after laying).
    2.5 bottom coating
    foundation drying with a special primer (TB-201) roll applied to the substrate, generally divided into two rolling coating, the foundation of low solidity requires multi-roll coating, the principle is to paint the base surface to form a bright continuous film so far. The role of primer is to penetrate the micro-hole of the substrate, to block the groundwater gas and strengthen the substrate, to form a bright film is to ensure that the micro-hole of the substrate is completely blocked, should avoid the hot sun or the substrate temperature is too high (>50 degrees C) under the circumstances of construction, to ensure the permeability of the primer.
    2.6 Water accumulation repair
    where the water depth at the water accumulation is not more than 5mm, use an elastic layer (TB-002) plus quartz powder (or talcum powder) by 1:1 (weight ratio), mix the thinner (toluene) well, and adjust to the appropriate construction consistency, Apply a straight ruler or scraper to the water accumulation, if the depth of water accumulation exceeds 5mm, apply a special primer (TB-201) plus 40 to 80 sand, according to 1:6 to 8 (weight ratio) mix and uniform, flat paved at the water accumulation and pressed. When repairing pay attention to repair edges, do not let the patched edges higher, if there is a higher need to polish flatten before the elastic layer construction.3 Silicon PU material construction
    3.1 elastic layer construction
    elastic layer construction should be carefully checked to confirm that the foundation treatment is complete before the elastic layer construction. Elastic layer (TB-002) for a single-part material, only need to use thinner to adjust the appropriate construction consistency, with tooth scraper scraped on the substrate, each scraping thickness can not exceed 2mm, each scraping interval for the previous dry solidification (generally about 10 hours, depending on the weather conditions on site) until scraped to the new required thickness. When applying scraping attention to the leveling effect, if you can not level the scratch marks, you need to add more thinner to adjust the consistency to ensure surface leveling.
    If the temperature is low (<10 degrees C) and humidity is low (<50%), 3% to 8% of the water must be stirred well and scraped, so that the drying time is shortened, depending on the weather on the spot. Work in the hot sun should be avoided. After the elastic layer is solidified, the surface flatness is tested by water accumulation method, and TB-002 is used to repair the flatness at the water accumulation. The surface has grainy debris mixed or accumulated place needs to be leveled with a grinder in order to strengthen the layer construction.
    3.2 Strengthening layer construction
    strengthening layer (TB-003) as a single-part material, construction use methods and elastic layer consistent. Dry solid surface requirements smooth, if mixed in the construction process of debris or uneven places need to be trimmed smooth before surface construction.
    3.3 surface construction
    surface layer (TB-205) as a two-part material, must be in accordance with the prescribed proportion of A, B two parts fully stirred evenly, can add a small amount of water to adjust the appropriate construction consistency, with ply scraping plate divided into 2 to 3 scrapes applied to the surface of the strengthening layer. The surface needs to be rough can be added ≤30% surface layer special sand, should first mix the A part and the special sand evenly and then add group B fully mixed evenly after scraping.
    (all kinds of court surface reference practices: table tennis, basketball court: the first to add 30% special sand, the second to add 15% special sand, the third road without special sand; Badminton, volleyball court: no special sand points 2 to 3 scraping). Surface construction materials must be sufficient, otherwise it will directly affect the effect of use and the duration of use. The construction should be avoided in the case of hot sun and high surface temperature, so as to ensure the surface effect.
    3.4 Dashing
    according to the standard size measure positioning, marking the boundary position, with the United States paper along both sides of the boundary on the pitch, with a special dash paint (TB-207) painted in the United States between the paper, to be dry after the surface to tear off the texture paper. TB-207 is a two-part material, must be in accordance with the prescribed proportion of A, B two parts fully mixed evenly, divided into two brushes. If the surface of the course is rough, the first one can be added 20% surface layer special sand brushing, to prevent seepage edges.
    3.5 Construction Precautions
    (1) the material must be weighed accurately and stirred evenly.
    (2) the construction of the whole process after each process of construction within 8 hours can not have water immersion.
    (3) indoor space must ensure good ventilation.
    (4) site needs to be maintained for more than 5 days before it can be put into use. 4 Conclusion
    This project combined with the specific situation, the use of silicon PU materials for basketball court construction is a successful practice, but also for the construction of the school dedicated a world of activities and achieved good social benefits.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.