    The central inspection team has been stationed in 7 provinces, just named the chemical environmental protection problem how to rectify?

    • Last Update: 2020-08-02
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    recently, the first batch of central environmental protection inspectors "look back" has been fully launched, six central environmental protection inspection teams to 10 provinces (autonomous regions) to carry out "look back" inspectors stationed.
    DbG .May 30
    DbGThe Third Environmental Protection Inspection Group of the Central Committee of the Central Committee of the Central Committee of the Central Committee of the Central Committee of the Third Environmental Protection Inspection Group stationed in Heilongjiang
    DbGMay 31
    DbGthe First Environmental Protection Inspection Group of the Central Committee of the Central Committee of the Central Committee of the Central Committee of the First Environmental Protection Inspection Group stationed in Hebei
    DbGJune 1
    The first environmental protection inspection group of the Central Committee of the DbGstationed in Henan
    the second environmental protection inspection group of theCentral Committee is stationed in Ningxia
    DbGthe fourth environmental protection inspection group of the Central Committee of theCentral
    Committee of the Central Committee of the Central Committee of the, China, on June 5,
    DbGCentral Fifth Environmental Protection Inspection Group, the
    CentralCommittee of the Central Committee of the Inspection Group, was stationed in theof theof the Central
    , The Ministry of Ecological Environment announced that eight provinces (regions) including Jilin, Zhejiang, Shandong, Hainan, Sichuan, Tibet, Qinghai and Xinjiang (including the Production and Construction Corps) have disclosed the central environmental protection inspection and rectification plan.
    DbG .Among them, Jilin, Zhejiang, Shandong, Sichuan four chemical provinces open rectification program, involving the chemical industry rectification situation is as follows:
    DbG Shandong
    DbG , "National Petrochemical and Chemical Industry" 12th Five-Year Development Plan" requires enterprises with greater environmental risks should enter the chemical park, but the provincial economic and information committee in the actual work did not put forward a clear request.
    DbG .  Time limit for rectification: by the end of 2025.
    DbG .  Rectification objectives: by the end of June 2018 to complete the chemical production enterprises "four ratings one evaluation", by the end of September 2018 to basically complete the park identified and determine the list of relocation and transformation enterprises; Outside the chemical park, it is strictly forbidden to build or expand chemical production projects.
    DbG .  Corrective measures:
    DbG (i) actively carry out rating evaluation, forcing enterprises to relocate or transform or shut down and turn. A list of all relocation and renovation enterprises will be finalized by the end of September 2018. To ensure that small and medium-sized enterprises and large enterprises with significant risks start relocation by the end of 2018, completeby by the end of 2020, other large enterprises and large enterprises by the end of 2020 to start relocation and renovation, by the end of 2025 to complete the closure or relocation work.
    DbG .  (2) Organize and implement the identification of chemical parks, and actively guide enterprises into the park.
    DbG .  (3) Strictly implement national policies and vigorously promote the relocation and transformation of enterprises with dangerous chemicals. Dangerous chemicals enterprises in principle into the professional chemical park, not in the park to gradually shut down and eliminate.
    DbG .  Second, some departments and local ities on the illegal construction, the province's chemical enterprises into the park rate of only about 20%, a large number of chemical projects illegal construction. At present, the province's 8,124 chemical enterprises in production, 3389 no project procedures, 5146 no planning clearance procedures, 3,259 no land procedures, 1183 no Environmental Assessment procedures.
    DbG .  Time limit for rectification: to set up reform, long-term adhere to.
    DbG .  Rectification objectives: all illegal construction projects immediately stop production and rectification. To promote chemical enterprises into the park, on the basis of the existing rate of 20%, and strive to reach 30% by 2020, 2022 to reach 40%.
    DbG .  Corrective measures:
    DbG (i) strengthen special rectification and deal with illegal items in accordance with the law.
    DbG .  (b) Promote entry into the park and strengthen the management of the park. Optimize the layout of chemical park, improve the rate of chemical enterprises to enter the park, achieve intensive concentration development, and strive to reach 30% by 2020 and 40% by 2022.
    DbG .  (3) Strengthen project management and strict project approval. The approval or filing authority for new construction, alteration and expansion of chemical projects shall be received from the competent department of investment at the municipal and municipal levels.
    DbG .  Third, some local violations to promote the construction of chemical enterprises.
    DbG .  Time limit for rectification: to set up reform, long-term adhere to.
    DbG .  Rectification objectives: immediately stop illegal activities, according to the law to carry out rectification, the deadline for rectification is not in place of the illegal construction of chemical enterprises resolutely banned.
    DbG .  Corrective measures:
    DbG (i) to no project, planning, land, environmental assessment and other procedures for chemical enterprises immediately stop production and rectification.
    DbG .  (b) Promote entry into the park and strengthen the management of the park. Overall consideration of regional environmental capacity, optimize the layout of chemical park, improve the rate of chemical enterprises to enter the park, to achieve intensive intensive development, and strive to reach 30% by 2020, 2022 to reach 40%. To strengthen the management of enterprises entering the park, new and expanded projects must enter the chemical parks, professional chemical parks and key monitoring points announced by the provincial government.
    DbG .  (3) Strengthen project management and strict project approval. The approval or filing authority for new construction, alteration and expansion of chemical projects shall be received by the competent department of investment at the municipal and municipal levels of the district, and the new and expansion hazardous chemicals projects with fixed assets of less than 300 million yuan (excluding land costs) shall not be approved or recorded in principle, except for innovative achievement conversion projects with products to fill domestic blanks or process technology to reach the leading domestic level.
    DbG .  Fourth, since 2013, Weifang City Shouguanghou Town Marine Chemical Park, Linyi City, Lushan Chemical Park, Binzhou Industrial Park and other breakthrough city master planning scope, respectively, the construction of 20, 37 and 8 chemical projects.
    DbG .  (i) Weifang City
    DbG rectification time limit: by the end of 2018.
    DbG .  Rectification objectives: strict park planning and management, strict control of the entrance project, the establishment of a standardized and orderly park planning adjustment and implementation procedures, to maintain the authority and seriousness of planning.
    DbG .  Rectification measures:
    DbG 1. Further improve the planning system of Houzhen Marine Chemical Park, resolutely maintain the authority and seriousness of the planning, under the guidance of planning and guidance to carry out the construction of the park project.
    DbG .  2. To evaluate the implementation of the Houzhen Master Plan (2016-2030) in accordance with the law.
    DbG .  (b) Linyi City
    DbG rectification time limit: by the end of March 2018.
    DbG .  Rectification target: 37 illegal chemical projects classified disposal, according to the norms of stop production and rectification.
    DbG .  Corrective measures: By the end of March 2018, all projects under construction within the scope of the urban master planning land breakthrough in Lushan Chemical Park will be stopped, and all production projects will be suspended and put off for rectification in accordance with the principle of "one enterprise, one policy" and all production projects involving people's livelihood, safe production and special production processes will be discontinued and corrected.
    DbG .  (3) Binzhou City
    DbG rectification time limit: In addition to the central disaster relief pesticide reserve project, the other 6 projects by the end of January 2018 to stop production and rectification.
    DbG .  Rectification objectives: 2 related to the central disaster relief pesticide reserve project production-limiting operation, the emission standards, the other 6 projects will be discontinued and rectification.
    DbG .  Rectification measures: For 3 unbuilt projects, ordered not to start construction. Limited production operation of products and their production lines in 2 pesticide reserve projects related to central disaster relief (pesticide raw drugs and preparations, S-isoproparide amine technical reform projects) is monitored in real time to ensure compliance with EIA requirements; Three other projects were ordered to stop production and rectify.
    DbG .  (4) Strict park identification, standard project management. In contrast to the central environmental protection inspector feedback on the three parks, one by one, the city has announced the chemical park to conduct a comprehensive mapping. By the end of September 2018, the chemical park identification work will be basically completed.
    DbG .  V. Shandong Kunda Biotech Co., Ltd. in May 2016 did not approve the first construction of two hazard-related chemical chemical seis chemical projects, the nature of the land does not meet the requirements of The establishment of the chemical concentration area in Shandong Province, Linyi Municipal Government in Response to the request of the Sushui County government, in November 2016 illegally identified the project area as a chemical concentration area, Sushui County according to the relevant procedures for the enterprise.
    DbG .  Time limit for rectification: to set up reform, long-term adhere to.
    DbG .  Rectification target: Shandong Kunda Biotech Co., Ltd. illegal project stop production and rectification.
    DbG .  Corrective measures: by the end of 2017, Shandong Kunda Biotech Co., Ltd. illegal construction of the pyridine deep processing and double ethylene ketone, acetyl acetyl ethyl ester two dangerous chemicals projects have been discontinued and rectification, all under construction projects all suspended. By the end of March 2018, the chemical projects of the enterprise to complete the procedures are not in line with the plan.
    DbG .  6. The total consumption of coal in Shandong Province is large, the proportion of high-polluting, high-energy-consuming industries such as chemical, cement and steel is high, the scale of production capacity such as electrolytic aluminum continues to grow, the total amount of major atmospheric pollutants is high for a long time, and the atmospheric environment situation is very serious.
    DbG .  Time limit for rectification: to set up reform, long-term adhere to.
    DbG .  Rectification objectives: chemical, cement and steel and other high-polluting, high energy-consuming industries energy utilization level sharply increased, product consumption continued to reduce, strict control of electrolytic aluminum and other new capacity, to the end of the "13th Five-Year Plan", the province's energy-consuming industries accounted for the proportion of industrial energy consumption above the scale to achieve a decline.
    DbG .  Corrective measures:
    DbG (i) strengthen project audit clearance. The implementation of energy intensity and total energy consumption "double control" from the source to control energy consumption.
    DbG .  (2) To adjust the industrial structure. Develop strategic emerging industries such as green low carbon, continuously strengthen the cultivation of high-end industries, optimize the distribution of productivity, and promote the development of green with high-end industry.
    DbG .  (iii) To optimize the energy structure. Strengthen the development and utilization of clean energy.
    DbG .  (4) Strengthen the basic management of energy conservation.
    DbG .  Some prominent environmental problems have not been effectively solved in the of dbG
    Zhejiang. 11 dye chemical enterprises in the town of Taoyu landfill 1248 million tons of hazardous waste, there are environmental hazards. Shaoxing Shangyu District Government pays insufficient attention to this, has not been properly disposed of for a long time. In November 2016, the Shaoxing municipal government included it in the city's list of major environmental hazards, requiring that the rectification in place as soon as possible. However, the Shangyu District Government will not begin to manage the
    DbG the time limit for rectification until the end of February 2018 after the On-site inspection by the Ministry of Environmental Protection in March 2017.
    DbG .  Rectification objectives: thoroughly clean up hazardous waste, comprehensively investigate and punish farm violations, and carry out ecological restoration of contaminated sites.
    DbG .  Corrective measures:
    DbG 1. Speed up the implementation of the clean-up. By the end of December 2017, hazardous waste excavation and clean-up work has been completed, and all qualified units of hazardous waste and suspected contaminated soil have been commissioned for standardized disposal;
    DbG .  2. Immediately ordered the farm to close down. On 28 August 2017, the farm was ordered to close its operations, and by the end of September 2017, illegal buildings on the farm had been demolished, plants on the site had been removed, and the relevant subsidy funds and honours received from the farm had been withdrawn.
    DbG .  3. Start ecological restoration project. By the end of February 2018, according to the expert review opinion, complete the construction of the main ecological restoration project, implement local soil cover backfilling and ecological restoration, and ensure monitoring indicators.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.