    The hydrogen production unit of the Beihai Refining and Chemical Reconstruction Project was successfully commissioned once

    • Last Update: 2021-06-09
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

      Sinopec News Network News At 11:30 on May 6th, the reformer of the hydrogen production unit of the Beihai Refining and Chemical Restructuring Project was successfully turned on and the oven was officially started, marking the official start of the hydrogen production unit.

      The 30,000 standard/hour hydrogen production unit uses PSA tail gas from the PSA unit and coking mixed dry gas from the product refining unit as raw materials, and is an important source of hydrogen supply after the structural adjustment and transformation project is put into use.
    The structural adjustment and transformation project is a key project in the 13th Five-Year Development Plan of Beihai Refining & Chemical Corporation.
    Construction will start in September 2019, and China Communications will be fully completed on April 22, 2021, officially entering the stage of preparation for the start of construction.

      The oven is the most critical step before the official start of the hydrogen production plant.
    In order to ensure the smooth realization of the expected goals, all personnel of the new plant will stick to their posts during the holiday season and complete various tasks before the ignition in strict accordance with the company’s deployment requirements, so as to make full preparations for the ignition.
    .
    In the preparation process, the company planned and organized carefully to strictly implement safety and quality grid management measures.
    The three refining departments actively cooperated with the operation and completed the preliminary work such as purge air tightness, power equipment trial operation, and fuel gas system introduction.
    The furnace lays a solid foundation.

      At present, other devices are also undergoing trial operation in an orderly manner, making every effort to promote the smooth start of the structural adjustment and transformation project.

      (Huang Jianyun)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.
    Related Articles

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent Echemi's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.