    The second phase of CGNPC's Hongyanhe nuclear power project entered the peak of installation of the main equipment of the nuclear island

    • Last Update: 2022-11-24
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On March 18, the reactor pressure vessel, the first nuclear island main equipment of CGN's Hongyanhe Nuclear Power Unit 5, arrived at the Hongyanhe nuclear power site, marking that the second phase of the Hongyanhe nuclear power project entered the peak
    of the installation of the main equipment of the nuclear island.

    After the pressure vessel of the No.
    5 reactor arrived at the site, the engineers transported it directly to the gantry of the No.
    5 nuclear island to prepare
    for the subsequent installation operation.

    The reactor pressure vessel, one of the most critical equipment of the nuclear power plant, is located in the center of the nuclear island plant, about 13 meters high, about 4 meters in diameter, and weighs more than 300 tons
    .
    It contains the reactor core, reactor components, control rods and other components, and is a container device
    for maintaining and controlling nuclear fission reactions.
    After the operation of the unit, the reactor pressure vessel will work under the state of 155 atmospheres and more than 300 degrees of high temperature and high pressure, and its manufacturing has the characteristics
    of high quality requirements, technical difficulty and complex process.
    The reactor pressure vessel of Unit 5 is produced
    by Shanghai Electric Nuclear Power Equipment Co.
    , Ltd.

    Unit 5 is the first unit of the second phase of the Hongyanhe Nuclear Power Project, which started construction
    on March 29, 2015.
    With the arrival of the No.
    5 reactor pressure vessel at the nuclear power plant, the unit will enter the peak
    of the installation of the main equipment of the nuclear island.
    At the end of this year, Unit 6 will also enter the installation stage
    of the main equipment of the nuclear island.

    The first phase of the Hongyanhe Nuclear Power Project was completed in 2016 to generate electricity
    .
    The second phase of the project is scheduled to be completed and put into operation in 2021
    .

    On March 18, the reactor pressure vessel, the first nuclear island main equipment of CGN's Hongyanhe Nuclear Power Unit 5, arrived at the Hongyanhe nuclear power site, marking that the second phase of the Hongyanhe nuclear power project entered the peak
    of the installation of the main equipment of the nuclear island.

    nuclear power

    After the pressure vessel of the No.
    5 reactor arrived at the site, the engineers transported it directly to the gantry of the No.
    5 nuclear island to prepare
    for the subsequent installation operation.

    The reactor pressure vessel, one of the most critical equipment of the nuclear power plant, is located in the center of the nuclear island plant, about 13 meters high, about 4 meters in diameter, and weighs more than 300 tons
    .
    It contains the reactor core, reactor components, control rods and other components, and is a container device
    for maintaining and controlling nuclear fission reactions.
    After the operation of the unit, the reactor pressure vessel will work under the state of 155 atmospheres and more than 300 degrees of high temperature and high pressure, and its manufacturing has the characteristics
    of high quality requirements, technical difficulty and complex process.
    The reactor pressure vessel of Unit 5 is produced
    by Shanghai Electric Nuclear Power Equipment Co.
    , Ltd.

    Unit 5 is the first unit of the second phase of the Hongyanhe Nuclear Power Project, which started construction
    on March 29, 2015.
    With the arrival of the No.
    5 reactor pressure vessel at the nuclear power plant, the unit will enter the peak
    of the installation of the main equipment of the nuclear island.
    At the end of this year, Unit 6 will also enter the installation stage
    of the main equipment of the nuclear island.

    The first phase of the Hongyanhe Nuclear Power Project was completed in 2016 to generate electricity
    .
    The second phase of the project is scheduled to be completed and put into operation in 2021
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.