    The Shizuoka hydroelectric power plant is expected to start operating in 22

    • Last Update: 2022-11-23
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On March 2, Central Japan Electric Power announced that it will add an Abe River hydroelectric power plant
    in Aoi Ward, Shizuoka City.
    The Abe River Hydropower Station generates electricity using a "water-flow" method that draws water through pipes, and outputs 7,100 kilowatts
    .
    The construction cost is expected to exceed 10 billion yen, and it is planned to start operation
    by 2022.
    It is expected that stable power generation will expand
    renewable energy through hydroelectric power generation.

    The hydropower plant is planned to draw water from the Abe River about 30 kilometers upstream of Shizuoka City, introduce the power station through a 4.
    8-kilometer pipeline waterway tunnel, and run the generator through a conduit with a drop of 121 meters
    .

    After completion, the annual power generation capacity will be about 38 million kilowatt hours, and it is expected to reduce carbon dioxide emissions by 18,000 tons
    .

    On March 2, Central Japan Electric Power announced that it will add an Abe River hydroelectric power plant
    in Aoi Ward, Shizuoka City.
    The Abe River Hydropower Station generates electricity using a "water-flow" method that draws water through pipes, and outputs 7,100 kilowatts
    .
    The construction cost is expected to exceed 10 billion yen, and it is planned to start operation
    by 2022.
    It is expected that stable power generation will expand
    renewable energy through hydroelectric power generation.

    electricity

    The hydropower plant is planned to draw water from the Abe River about 30 kilometers upstream of Shizuoka City, introduce the power station through a 4.
    8-kilometer pipeline waterway tunnel, and run the generator through a conduit with a drop of 121 meters
    .

    After completion, the annual power generation capacity will be about 38 million kilowatt hours, and it is expected to reduce carbon dioxide emissions by 18,000 tons
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.