    The total amount of central subsidy funds for biomass power generation in 2021 is 2.5 billion yuan

    • Last Update: 2021-09-13
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Recently, the National Development and Reform Commission, the Ministry of Finance, and the National Energy Administration jointly issued the "2021 Biomass Power Generation Project Construction Work Plan
    .


    " According to the "Work Plan", the total amount of central subsidy funds for biomass power generation in 2021 will be 2.


    The "Work Plan" pointed out that the biomass power generation projects declared for the central subsidy in 2021 are divided into non-competitive allocation projects and competitive allocation projects
    .


    After January 20, 2020 (inclusive), the projects in which all units are completed and connected to the grid in the current year but are not included in the scope of subsidies in 2020 and the projects that start construction before the end of 2020 and all the units are completed and connected to the grid before the end of 2021 are non-competitive configuration projects; 2021 After January 1st (inclusive), the newly started projects in the current year are competitive allocation projects


    The "Work Plan" clarified that the total amount of central subsidy funds for biomass power generation in 2021 will be 2.


    5 billion yuan, of which: 2 billion yuan will be used to arrange non-competitive allocation projects and 500 million yuan will be used for competitive allocation projects (including: agricultural and forestry biomass power generation and biogas power generation 3 100 million yuan, 200 million yuan for waste incineration power generation)


    In accordance with the overall idea of ​​"shared by the central and local governments," the "Work Plan" pointed out that the subsidies for all grid-connected projects before September 11, 2020 will be borne by the central government
    .


    After September 11, 2020 (inclusive), the subsidy funds for all grid-connected projects will be shared by the central and local governments.
    The central support ratio for different types of projects will be reasonably determined according to the eastern, central, western and northeastern regions, and the local governments will solve the shared funds through multiple channels.


    Specifically, the western and northeastern regions (Inner Mongolia Autonomous Region, Liaoning Province, Jilin Province, Heilongjiang Province, Guangxi Zhuang Autonomous Region, Hainan Province, Chongqing City, Sichuan Province, Guizhou Province, Yunnan Province, Tibet Autonomous Region, Shaanxi Province, Gansu Province, Qinghai Province Province, Ningxia Hui Autonomous Region, Xinjiang Uygur Autonomous Region and Xinjiang Production and Construction Corps) the central support ratio for agricultural and forestry biomass power generation and biogas power generation projects is 80%; the central support ratio for waste incineration power generation projects is 60%
    .


    Central regions (Hebei, Shanxi, Anhui, Jiangxi, Henan, Hubei, Hunan) agricultural and forestry biomass power generation and biogas power generation projects have a central support ratio of 60%; waste incineration power generation projects have a central support ratio of 40%


    Regarding the specific rules to be included in the central subsidy in 2021, the "Work Plan" pointed out that non-competitive configuration projects will be included in order according to the completion and grid connection time of all units.


    If the grid connection time is the same, the cogeneration project will be given priority and the installed capacity will be given priority.
    Included until the total amount of central subsidies required for the inclusion of the project reaches the corresponding subsidy fund quota


      In order to promote the orderly construction of biomass power generation, the "Work Plan" emphasizes that the central share of biomass power generation subsidies will be adjusted and withdrawn in an orderly manner year by year, and the scale of central subsidies for competitive allocation will be increased year by year
    .


    Encourage non-competitive allocation projects to participate in competitive allocation


      In addition, the "Work Plan" also gives clear construction deadlines for various projects
    .


    Competitive allocation projects included in the scope of central subsidies in 2021 should be completed and connected to the grid by the end of 2023.
    The grid-connected electricity price subsidy will be reduced by 0.
    03 yuan/kWh for every quarter of the actual grid-connected time



      Transfer from: China Energy News

      

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.