    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    Epoxy thin coating paint is a two-component, roll-on, seamless high-performance epoxy floor coating produced from high-quality raw materials, the coating surface is smooth and beautiful, durable.
    construction
    mixing
    mixing, low speed (300 to 500rpm) electric mixer should be used. The paint should be fully stirred so that the sediment is dispersed evenly, and then the curing agent is added to the container filled with the paint, stirring time is about 3 minutes, once the mixing is complete, the construction
    construction parameters
    mixing ratio (weight ratio) should be carried out immediately. ): Finish: Curing agent: 4:1
    after mixing service life (25 degrees C): 30 minutes, the higher the temperature, the shorter the service life after mixing, the ambient temperature at construction is higher than 35 degrees C, generally not recommended for construction
    thinner If construction viscosity needs to be reduced, a thinner of no more than 3% of the coating weight can be added, the diluent is SDP-501X
    drying time: table dry: ≤4 hours ≤
    ; Interval: After confirming that the coating has been completely dried before the next process construction, usually in the standard environment interval time of 24 hours
    explain: the drying time is determined under standard conditions (25 degrees C, 50% relative humidity), for reference only
    China
    . There are big differences in the drying speed at different temperatures and humidity, but also by the thickness of the paint film, ventilation conditions, lower coatings and so on. Typically, the drying time is shortened when the temperature increases, and when the temperature decreases, the drying time is lengther
    construction mode
    roll coating:
    spraying is used for large area construction:
    brushing is possible with conventional spraying or airless spray equipment: When using in small areas and corner areas, soft brush
    construction procedures
    economy epoxy floor coating system is based on epoxy thin coating as a surface material and does not contain mortar coating system. The coating structure is simple and low cost, which can be used for floor coating of a better flat base surface, or in the case of low decorative and pressure resistance performance.
    sanding clean ground: requires the ground without coarse particles, no cement, no dust, flatness of 2m by the ruler is not greater than 3mm
    bottoming: before bottoming requires the surface without dust and loose sand particles. Use epoxy-enclosed primer to base, ordinary roller brush brush, to strengthen the substrate, closed cement surface capillary holes, enhance paint adhesion. Requires uniform coating, no leakage
    scraping putty: use solvent-free epoxy medium paint mixed with the appropriate amount of quartz powder or talcum powder with putty scraping 1 to 2 times, after drying the batch knife marks and other defects and clean up. Requirements are not permeable, no sand, surface no sand eye
    roll paint: with epoxy thin paint roll coating 1 to 2 times. Requires uniform color, no obvious brush lines and connectors, no leakage brush, no permeable bottom, no foaming
    coating system structure schematic (see below)
    epoxy mortar floor coating system is a combination of epoxy thin coating paint and epoxy anti-pressure anti-erring mortar coating system. With high coating thickness, high pressure strength, wear resistance, impact resistance, smooth and beautiful surface, durable and so on, suitable for the floor coating requirements of high places to use.
    sanding clean ground: requires the ground without coarse particles, no cement, no dust, flatness of 2m by the ruler is not greater than 3mm
    bottoming: before bottoming requires the surface without dust and loose sand particles. Use epoxy-enclosed primer to base, ordinary roller brush brush, to strengthen the substrate, closed cement surface capillary holes, enhance paint adhesion. Requires uniform coating, no leakage
    scraping mortar: using solvent-free epoxy medium paint mixed with the appropriate amount of 40 to 100 quartz sand, with scraper scraping to the set thickness, requires the mortar surface particles uniform, sand Grain no shedding phenomenon
    scraping putty: using solvent-free epoxy medium paint mixed with the appropriate amount of quartz powder or talcum powder with putty scraping 1 to 2 times, after drying the batch knife marks and other defects and clean up. Requirements are not permeable, no sand, surface no sand eye
    roll paint: with epoxy thin paint roll coating 1 to 2 times. Requires uniform color, no obvious brush lines and connectors, no leakage brush, no bottoming, non-foaming
    coating system structure schematic (see figure below)
    sergic note
    after construction, with thinner cleaning coating tool equipment, the cured paint stain, mechanical method to remove
    special statement
    this product should not be used in direct sunlight or ultraviolet intensity of the occasion
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.