    Zhengzhou residents 45 days decoration dry 11 months of engineering said rework is not a period of time.

    • Last Update: 2020-09-11
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    China Paint Network
    :
    days, Mr. Tang every day, this is from September 18 last year he signed a construction contract with the decoration company. According to the contract, the new house should be completed in 45 days, but enough to delay to this year's National Day, extended for 11 months, the two sides still exist money, compensation disputes. What's going on in the middle of this? Troubled decoration: paint less brick floor leakage Mr. Tang's house is located in Zhengdong New District Longzi Lake Agricultural District, to Henan Yishan Decoration Engineering Co., Ltd. decoration. "I'm usually busy thinking that Art is still a chain of big companies, I didn't expect a lot of problems after the renovation." Mr. Tang said angrily. Mr. Tang said that a month and a half after the normal delivery time, in late December 2014, the construction team informed him that the renovation was complete. "The whole house is full of problems, the walls can't be touched at all, a touch on the 'whispering' down the powder, tiles are also attached here less than one piece there less. At that time, I contacted their decoration company a manager surnamed Li came over, he also admitted that there is a problem, promised to repair, then I mentioned the extension of compensation, but he smiled and said after the installation. "From a screenshot of Mr. Tang's cell phone message, it was not until the end of May this year that the construction team finished the bricks and repainted them. Prior to the construction team has been in the field, understuged and other reasons for pushing and dragging. In addition to the extension of the construction period, in the early stage of renovation, Mr. Tang found that his family 5 floor leakage 4 are bad, especially the shower room leakage, completely unable to go into the water, was sealed by cement. "At that time, the project did not take long to repair, they also promised to repair, but they bought the ground leakage does not match, do not need to say, that sealed also did not open, nor re-installed, is the surface moved." The height of the leak also exceeds the horizon, the water does not flow in, but can only be laid on the original tiles on another layer. Does rework count as duration? According to the contract, three days before the start of construction, Mr. Tang paid about 28,850 yuan for 55% of the project. Since then, in addition to Mr. Tang's own choice of tiles,
    paint
    , the rest are the responsibility of the decoration company. Halfway through the renovation, Tang Xian
    sheng paid 40% of the project in accordance with the contract about 21,000 yuan, only 5% of 2604 yuan outstanding, according to the contract this 2000 yuan should be paid on the basis of acceptance. "I offered an extension because the contract clearly stated that two thousandths of a thousandth of the compensation would be paid for each delay, but the decoration company did not admit that there was an extension, and the Manager Li said that he could pay less as compensation, and I certainly wouldn't." Mr. Tang said angrily, "Because the delay is too long, I can't return any extra tiles, at least about 1000 yuan." "So far, Manager Li of Henan Yishan Decoration Engineering Co., Ltd. has said that the project is only delayed by one month, and the rest are rework and maintenance caused by the owner's dissatisfaction, and are not included in the construction period. Reporters found that the contract clearly states that
    delay in the delivery of the work due to the rework of the project is regarded as a project delay". In this regard, Li manager did not give any explanation, only stressed that he is the company's management personnel, the project is not understood, need to verify the reply, after the mobile phone has been shut down. Mr. Tang said he would defend his legitimate rights and interests through the law. "San Yun, a lawyer at Henan Guoji Law Firm, believes that in this case, according to the available materials, the decoration company has constituted a breach of contract, and Mr. Tang may claim to the other party in accordance with the relevant provisions of the Contract Law to take remedial measures or compensation for losses, payment of breach of contract and other breach of contract liability to safeguard his legal rights. If it constitutes an infringement, the decoration company may also be required to bear tort liability.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.