    Another PDH will be put into production!

    • Last Update: 2022-08-24
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On August 17, the company's Ningbo Donghua Energy PDH substation successfully received electricity for one time


    .


    In order to ensure the smooth implementation of the 35KV power reception work, Ningbo Donghua Energy PDH Project Department established a power reception work group, organized all parties to carry out special inspections and problem elimination in advance, and carried out detailed plan review, technical disclosure, emergency plan and measure inspection.
    and other work


    .


    Ningbo Donghua Energy PDH Project Department will take this opportunity to lead the high-standard construction of the project with high-quality party building, build PDH high-quality projects with refined management, and meet the company's "anti-epidemic guaranteed income, double-hundred battle" work requirements.


    In order to ensure the smooth implementation of the 35KV power reception work, Ningbo Donghua Energy PDH Project Department established a power reception work group, organized all parties to carry out special inspections and problem elimination in advance, and carried out detailed plan review, technical disclosure, emergency plan and measure inspection.
    and other work


    .


    Ningbo Donghua Energy PDH Project Department will take this opportunity to lead the high-standard construction of the project with high-quality party building, build PDH high-quality projects with refined management, and meet the company's "anti-epidemic guaranteed income, double-hundred battle" work requirements.
    Most practically, make persistent efforts to steadily advance the installation and completion of the PDH device and the follow-up commissioning work, and deliver a satisfactory answer to the owner and the company


    .


    Donghua Energy's Ningbo production base currently has a set of continuous reproduction 660,000 tons/year PDH unit and 400,000 tons/year PP unit applying UOP process.
    The second phase of the project will double the production scale of the existing units


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.