    Record of construction of Jinhang furnace pilot plant project

    In order to find a way out for the lump coal market, help coal chemical companies to transform and upgrade, turn losses and get out of trouble, Jinmei Group actively explored the Jinhang Furnace project, a coal gasification innovation project of military-civilian integration energy revolution, and pioneered "Bring the stove to sell coal.


    Strategize

    Jinhang Furnace is based on the numerous research results of current slag gasification technology, and based on the coal characteristics of Jinmei Group’s largest production of anthracite lump coal, it breaks through the fixed bed pressurized slag gasification technology of anthracite lump coal.


    The Jinhang Furnace Pilot Plant Project aims to solve the matching problem of Jincheng anthracite lump coal and slag gasification technology, and realize the pressurized slag gasification of coal with high ash melting point


    Overcome difficulties and rise to the challenge

    Seizing the time means seizing the opportunity


    On July 5, the cranes of the compression workshop with a span of 22.


    On July 11, the large-scale equipment desulfurization tower with the highest hoisting height and the highest safety factor was successfully lifted and accurately placed in place, and it was perfectly docked with the steel column under the desulfurization tower frame


    The progress of the project is advancing little by little: high-rise concrete pouring is completed in civil construction; various process pipelines are optimized and checked; 1# synthetic ammonia system 4 pure oxygen gasifiers are installed; a complete set of desulfurization drum filter equipment and sulfur foam tanks are in place; The civil construction of Shuangjia and the ice machine was completed; the compression low-pressure platform and the pipe frame foundation were poured, and the backfill was completed; the civil construction of the control room was basically completed.


      Dare to break, dare to do, dare to break, dare to try

      If you compare the construction of the Jinhang Furnace Pilot Project to a battle, then how to command this battle is a consideration of the wisdom and ability of decision-makers and managers


      Beat time


      Dare to be the first


      Innovative forms




    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.