Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
2021 is an important year for the construction of Huating Coal Industry's polypropylene project to be fully completed and commissioned
.
The polypropylene project preparatory office closely focused on the goals determined at the meeting, implemented targeted policies, made precise efforts, worked hard on safety, quality and progress, and ensured the high level of project construction
.
Up to now, the main pipeline air purging and low-pressure steam purging of the main unit of the project have been completed; the installation of the tower internals, the single test of the pump and the chemical cleaning are nearing completion; the ground torch ignition test, the extruder and the three major units oil transportation, catalyst Filling, system airtightness, and DCS system debugging have been fully started; the public material instrument air, compressed air, desalinated water, and low-pressure steam pipeline networks have been established and put into use normally
.
On the basis of grasping the progress of the project, the Preparatory Office of the polypropylene project strictly controls the safety and quality
.
In order to ensure the quality of the project, the management personnel at all levels in the department strengthen on-duty duty, adopt the side-by-side management method, and synchronize the work and rest time with the construction unit
.
At present, the installation of the main body of the boiler and the main body of desulfurization and dust removal has been completed; the main auxiliary equipment of the boiler, the high-pressure dewatering pump, the high-pressure heater, and the primary and secondary fans have been installed in place, and the water pressure test of the main body of the boiler and the boiler construction have been successfully completed.
The steam and main water supply pipelines were installed, and the integrated pipe gallery of the boiler unit was connected; the water inlet commissioning of the circulating water unit was advanced in an orderly manner; the single test of the motor of the desalination unit was completed
.