Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on May 25 that the manhole of the C-115 scrubber M1 of the C-115 scrubber of the EO/EG installation of the Gulei integration project in Nanjing Engineering was closed, and the installation of the internals of the tower which lasted for 2 months was successfully completed.
Affected by the epidemic, the arrival of the tower internals was delayed, resulting in a very tight installation period.
In order to ensure the construction nodes, the project department meticulously planned, coordinated, organized the participating units to study the internal drawings of the equipment, combined with the actual situation of the site, and under the premise of ensuring safety, the original three The number of work areas has been increased to 6, which greatly shortened the construction period, used space to grab time and regained the project schedule.
Before the tower internals were installed, after the on-site inspection of the pre-welded supports and the cleanliness of the tower, the staff found that some of the actual conditions did not match the drawings.
With the completion of the installation of the internals of the EO/EG device tower, the project's confined space operations are all completed and the final stage is entered.
(Li Jiajun Li Shu)