    On April 20, the extrusion granulation area and pellet blending area of ​​the Liaoyang Petrochemical 300,000-ton/year high-performance polypropylene project undertaken by the Liaoning Branch of Jilin Chemical Construction of Huanqiu achieved high-standard handover as scheduled


    It is understood that the extrusion and granulation area of ​​the 300,000-ton/year high-performance polypropylene project of Jilin Chemical Construction Liaoyang Petrochemical Company of Huanqiu involves 9 professional constructions including civil engineering, steel structure, equipment, process piping, electrical, instrumentation, anti-corrosion, fire prevention, and thermal insulation.


    It is understood that the extrusion and granulation area of ​​the 300,000-ton/year high-performance polypropylene project of Jilin Chemical Construction Liaoyang Petrochemical Company of Huanqiu involves 9 professional constructions including civil engineering, steel structure, equipment, process piping, electrical, instrumentation, anti-corrosion, fire prevention, and thermal insulation.
    Task, from the start of civil construction on October 10, 2019 to April 20, 2021, Global Jilin Chemical Construction Liaoning Branch has completed a total of 4,353 cubic meters of concrete, 228 tons of steel structures, 92 sets of equipment, 10,031 equivalents of process pipes, and electrical equipment.
    85 sets of electrical cables, 67,000 meters of electrical cables, 197 sets of instrumentation equipment, 40,200 meters of cables, 6,840 square meters of structural anti-corrosion, 470 square meters of steel structure fire protection, and 115 cubic meters of heat preservation

    .
    The pellet mixing area has been handed over to our unit since September 30, 2020.
    As of April 20, 2021, a total of 365 tons of steel structures, 46 sets of equipment, 19,978 equivalents of process pipeline welding, and 10,800 square meters of steel structure anticorrosion have been completed

    .
    At present, the civil engineering, steel structure, equipment installation, process pipeline installation, electrical, instrumentation, anti-corrosion, equipment thermal insulation and other work in the above two areas have been installed, which meet the requirements of design and specification standards, and the extrusion and granulation room has been cleaned.
    Safety facilities are in place

    .
    The high-standard transfer of the extrusion granulation unit has laid a solid foundation for the subsequent construction of the project and the comprehensive transfer of the 5.
    30

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.