    Sinochem Sixth Construction Co., Ltd. participated in the construction of Wanhua Chemical's 1 million tons/year ethylene project

    • Last Update: 2022-08-25
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On November 9, Wanhua Chemical's 1 million tons/year ethylene project, which was built by China Chemical Engineering Sixth Construction Co.
    , Ltd.
    Ningbo Branch, produced qualified products and was successfully completed and put into operation


    .


    Sincerely cooperate to build an excellent team

    Sincerely cooperate to build an excellent team

    In 2018, the project area was still deserted


    .


    The ethylene project is the core of the second phase project of Wanhua Yantai Industrial Park.
    It adopts international advanced technology and Wanhua's independent research and development technology, and is committed to building a high-level domestic ethylene industry chain


    .


    To this end, Sinochem Sixth Construction has paid close attention to the progress, safety and quality of the construction, and reasonably arranged the construction personnel, and the construction peak personnel reached thousands of people


    .


    It is understood that in recent years, the project team has established a construction team working mode with full participation and division of labor based on its own competitive advantages


    .


    Dare to take the lead in equipment hoisting and rise to the fort

    Dare to take the lead in equipment hoisting and rise to the fort

    On January 8, 2019, the 450-ton reactor of the LLDPE unit of the ethylene project was successfully hoisted, which opened the curtain of the hoisting work of the entire project equipment


    .


    In order to ensure the successful completion of this hoisting task, the project management team made strict arrangements and repeatedly scrutinized the installation plan


    .


    The polymerization reaction frame cooler of the HDPE unit is 60 meters long, 9 meters high, and weighs 200 tons.
    After research, Sinochem Sixth Construction decided to hoist the cooler as a whole


    .


    The steel structure construction and equipment hoisting of the extrusion granulation plant are the key points and difficulties in the construction of the LLDPE plant.
    The total height of the frame is 94.
    7 meters, of which 57.
    8~94.
    7 meters are steel structure frames.
    The total weight of the steel structure is 362 tons, which is the entire large ethylene area.
    the commanding heights

    .
    In order to reduce high-altitude operations, improve labor efficiency, and reduce costs, Sinochem Sixth Construction divided the steel structure frame into three modules for prefabrication.
    Complete all lifting work

    .

    Anti-epidemic and resumption of work together

    Anti-epidemic and resumption of work together

    Entering 2020, the sudden outbreak of COVID-19 disrupted the rhythm of project construction
    .
    Sinochem Sixth Construction is a central enterprise stationed in Hubei, so a large number of employees were stranded in Hubei, and the project construction was stagnant for a time

    .

    At critical moments, the company's management and project team showed strong emergency response capabilities
    .
    Project managers who are isolated at home are actively working through online meetings and other means

    .
    Based on the general principle of "getting out, getting in, and living down", the Zayan team combined with the general idea of ​​"first within the province, then outside the province, and finally Hubei", while researching and deploying epidemic prevention and control work, while combining various Formally guarantee the resumption of work and production of enterprises

    .

    After February, Ningbo Branch has communicated with the company headquarters, the owner and the government for many times.
    After repeated consultations and careful arrangements, a total of nearly 50 "point-to-point" buses have been opened from Shandong, Shanxi, Henan and other provinces.
    Nearly 1,000 employees have resumed work and production in an orderly manner in batches

    .

    On March 8, the first batch of buses carrying 20 managers from Xiangyang, Hubei arrived at Yantai Development Zone, and the return of Hubei employees to work officially kicked off
    .

    On March 25, the G3228 Xiangyang-Yantai Fuxing train set off for rework and arrived at Yantai Railway Station on time at 20:33.
    476 Hubei employees arrived at the workplace safely

    .
    Several leaders of Xiangyang Municipal Government and Sinochem Sixth Construction Company saw off the special train employees, and instructed the returning employees to go all out to prevent and control the epidemic, and to face difficulties and increase speed and efficiency in the boom of resumption of work and production.
    , and strive to create high-quality projects

    .

    Sounded the horn, fought continuously and successfully completed the transfer

    Sounded the horn, fought continuously and successfully completed the transfer

    More than half of 2020, accompanied by the hot summer, the big vinyl project sounded the clarion call
    .
    In order to ensure the smooth handover of the installation, the management personnel and construction team of Sinochem Sixth Construction gave up rest, and voluntarily participated in this "battle sprint" at the work rhythm of "61150" (that is, work at 6:00 a.
    m.
    for 50 consecutive days and leave at 11:00 p.
    m.
    that night).
    in

    .

    Faced with the enthusiastic "baking" test of the scorching sun and high temperature, Ningbo Branch has distributed enough mineral water and anti-heat-reducing medicines to fully do a good job in preventing and cooling down
    .
    All functional departments of the branch and other project employees also assisted with all staff, holding brooms and shovels on their shoulders, to carry out garbage cleaning work that lasted for nearly a month

    .

    After continuous "white + black" struggles, multiple units of the project have been handed over in batches, and the previous drawings have become real valves and pipelines in front of you
    .
    Under the collaborative model of "special class + support", everyone worked together to form a strong joint force, and finally successfully realized the mid-term handover of the project

    .

    One of the project members celebrated his birthday during the big run
    .
    He said that he was very happy to see the brightly lit, splendid night view of the project.
    "This is the most special gift

    .
    "

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.