Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on July 2, the Gulei Refining and Chemical Integration Project 800,000 tons/year No.
8 cracking furnace of the Gulei refining and chemical integration project undertaken by the Tenth Construction Company of Refining and Chemical Engineering successfully completed the drying target, marking the start of the cracking furnace.
.
It is understood that the 800,000-ton/year ethylene plant of the Gulei Refining and Chemical Integration Project has a total of 8 cracking furnaces, including construction tasks such as 3,500 tons of steel structure and 350,000-inch diameter of process pipelines, which are the core part and key to the construction of the entire ethylene project.
Line
.
Since the construction of the first cracking furnace started, the Shijian Gulei Refining and Chemical Ethylene Project has been guided by "management innovation and efficiency improvement", centered on the goal of cracking furnace oven nodes, breaking the traditional cracking furnace construction organization mode, The 3 cracking furnaces No.
The project department opened a second construction site around the ethylene plant site to conduct centralized prefabrication, overall transportation and installation of 3 cracking furnaces.
The construction efficiency has been significantly improved, which is 3 months earlier than the original planned construction period, while reducing the labor intensity of the participating employees.
, To reduce cross-working, lifting and hoisting and other hidden dangers of various safety risks, and to improve the quality of professional construction such as pipelines, equipment, electrical instruments, and anti-corrosion insulation
.
The overall modular construction of the cracking furnace has become a "new engine" and "booster" for accelerating the construction of the entire ethylene plant project
At present, with the successful completion of the cracking furnace and oven work, the construction staff of the project department are closely cooperating with the owner's workshop personnel to make preparations before feeding to ensure that the ethylene plant is safe, high-quality, and efficient to achieve the goal of one-time start-up feeding
(Tian Yuanwu)