Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
In the past few days, the 800,000-ton/year ethylene plant construction site of the Gulei Refinery and Chemical Integration Project undertaken by the Tenth Construction Company of Refining and Chemical Engineering has been booming, machines roared, and vehicles shuttled at the construction site, showing a bustling scene.
The entire project construction ran out "acceleration"
.
It is understood that the hoisting of the 800,000-ton/year ethylene plant equipment is in the early stage of construction, and more areas need to be reserved for the hoisting of large pieces on site, and foundation treatment should be carried out
.
The project department adheres to the idea of "safety first, prevention first", while doing safety training, safety education runs through the whole process of construction
.
As of March 30, the number of on-site construction workers of the ethylene plant reached 905, 63.
8% of the total civil construction was completed, 73.
2% of the total underground pipe network was completed, and the inner and outer walls of 4 buildings such as the ethylene substation and the cabinet room were completed.
The decoration is completed, the concrete pouring of the frame foundation of the three compressor units has come to an end, and the safety, quality and progress of the entire project construction are always under control
.