    The core equipment of the PDH unit of Guangxi Huayi's 750,000 tons/year propylene and downstream deep processing integration project arrived at the port

    • Last Update: 2022-08-29
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    Full start


    .


    The four towers, including the propylene-propane separation tower and the deethane stripping tower, which arrived at the port this time, were shipped from the new terminal of Zhangjiagang Port on September 30, with a total weight of about 3,300 tons, of which the diameter of the propylene-propane separation tower was 10.
    6 meters.
    With a height of 113.
    7 meters and an empty weight of 1537 tons, it is the largest, heaviest and most core equipment of the propane dehydrogenation unit of Guangxi Huayi's 750,000 tons/year propylene and downstream deep processing integrated project


    .


    us">
    The four towers, including the propylene-propane separation tower and the deethane stripping tower, which arrived at the port this time, were shipped from the new terminal of Zhangjiagang Port on September 30, with a total weight of about 3,300 tons, of which the diameter of the propylene-propane separation tower was 10.
    6 meters.
    With a height of 113.
    7 meters and an empty weight of 1537 tons, it is the largest, heaviest and most core equipment of the propane dehydrogenation unit of Guangxi Huayi's 750,000 tons/year propylene and downstream deep processing integrated project


    .


    Guangxi Huayi 750,000 tons/year propylene and downstream deep processing integration project, as the second phase project of Huayi Group Qinzhou Chemical New Material Integration Base, with a total investment of about 12.
    8 billion yuan, officially started construction on November 27, 2019.
    It is planned to It will be completed in September 2022 and put into operation at the end of the year.
    After the project is completed and put into operation, the annual sales revenue is expected to reach 10.
    2 billion yuan


    .
    It is understood that the main construction contents of the project include a 750,000-ton/year propane dehydrogenation unit, a 300,000-ton/year oxo-butanol unit, a 400,000-ton/year acrylic acid unit, a 400,000-ton/year butyl acrylate unit, and a 84,000-ton/year butyl acrylate unit.
    /year refined acrylic acid unit, 230,000 tons/year cumene unit, 280,000 tons/year phenol acetone unit, 200,000 tons/year bisphenol A unit and other process units, as well as supporting substations, circulating water fields, refrigeration units Station, air compressor station, intermediate storage tank, raw material and finished product tank area, torch, finished product warehouse and other public works and auxiliary facilities

    .
    Guangxi Huayi 750,000 tons/year propylene and downstream deep processing integration project, as the second phase project of Huayi Group Qinzhou Chemical New Material Integration Base, with a total investment of about 12.
    8 billion yuan, officially started construction on November 27, 2019.
    It is planned to It will be completed in September 2022 and put into operation at the end of the year.
    After the project is completed and put into operation, the annual sales revenue is expected to reach 10.
    2 billion yuan

    .
    It is understood that the main construction contents of the project include a 750,000-ton/year propane dehydrogenation unit, a 300,000-ton/year oxo-butanol unit, a 400,000-ton/year acrylic acid unit, a 400,000-ton/year butyl acrylate unit, and a 84,000-ton/year butyl acrylate unit.
    /year refined acrylic acid unit, 230,000 tons/year cumene unit, 280,000 tons/year phenol acetone unit, 200,000 tons/year bisphenol A unit and other process units, as well as supporting substations, circulating water fields, refrigeration units Station, air compressor station, intermediate storage tank, raw material and finished product tank area, torch, finished product warehouse and other public works and auxiliary facilities

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.