    The first phase of ExxonMobil Huizhou ethylene project with a total investment of 34.29 billion yuan was approved

    • Last Update: 2022-08-21
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Recently, the first phase of ExxonMobil Huizhou ethylene project was approved by the Guangdong Provincial Development and Reform Commission


    .


    The project is expected to start construction in June 2020 and be completed and put into operation by the end of 2023
    .


    Huizhou Development and Reform Bureau, ExxonMobil (Huizhou) Chemical Co.
    , Ltd.
    :

    The report has received the "Request for Instructions on Reporting the Approval of the ExxonMobil Huizhou Ethylene Phase I Project" (Hui Shi Fa Gai [2019] No.
    221) and related materials


    .


    1.
    In order to implement the "Guangdong-Hong Kong-Macao Greater Bay Area Development Plan", promote the high-quality development of petrochemical industry in our province, and accelerate the construction of a modern industrial system with international competitiveness, in accordance with the "Administrative Licensing Law", "Enterprise Investment Project Approval and Filing Administrative Regulations, the State Council's Notice on Issuing the Catalogue of Government-Approved Investment Projects (2016 Version) (Guo Fa [2016] No.
    72), and the Administrative Measures for the Approval and Filing of Enterprise Investment Projects (Order No.
    No.
    2) and the "Petrochemical Industry Planning and Layout Plan (Revised Edition)" (Fa Gai Industry [2018] No.
    1134) and other relevant regulations, agreed to build the ExxonMobil Huizhou Ethylene Phase I Project (project code: 2019-441303- 26-02-005879)


    .


            The project unit is ExxonMobil (Huizhou) Chemical Co.
    ,


    Ltd.


            2.
    The project construction site is Huizhou Daya Bay Petrochemical Industrial Zone (Huizhou Daya Bay Economic and Technological Development Zone)


    .


            3.
    The
    project builds a 1.
    2 million t/a crude oil direct cracking unit to produce ethylene and downstream polymers and supporting facilities.
    The main units include:
    5.
    79 million t/a crude oil desalination unit, 1.
    2 million t/a ethylene cracking unit, 850,000 t/a Linear low density polyethylene plant, 500,000 tons/year low density polyethylene plant, 450,000 tons/year impact copolymer polypropylene plant, 400,000 tons/year homopolymer polypropylene plant, 200,000 tons/year butadiene pumping plant Extraction unit, 140,000 tons/year diisobutene unit, 100,000 tons/year butene-1 unit, 1.
    45 million tons/year pyrolysis gasoline hydrogenation unit, 600,000 tons/year aromatics extraction unit, 600,000 tons/year chemical Clean fuel device, 50,000 tons/year sulfur recovery combined device,


    etc.


    The project builds a 1.


    The total investment is 34.


            6.
    The relevant documents for project approval are: Reply Letter of the General Office of the National Development and Reform Commission and the General Office of the Ministry of Industry and Information Technology on Converting the ExxonMobil Huizhou Ethylene Phase I Project from a Reserve Project to a Planning Project (Development and Reform) Office Industry [2019] No.
    651), Guangdong Provincial Department of Natural Resources "Reply to Opinions on Whether ExxonMobil Huizhou Chemical Complex Project Needs to Apply for Site Selection Opinions" (Guangdong Natural Resources Control Letter [2019] No.
    298) and "Pre-examination Opinions on ExxonMobil Huizhou Chemical Complex" (Guangdong Natural Resources (Huizhou) Letter [2019] No.
    1), National Development and Reform Commission and Ministry of Natural Resources "About ExxonMobil Huizhou Chemical Complex" Reply Letter on the Project’s Reclamation and Land Reclamation Projects on the Use of the Sea” (Fa Gai District [2019] No.
    1186), Huizhou Municipal People’s Government Office “Review Opinions on the Social Stability Risk Assessment Report of ExxonMobil Huizhou Chemical Complex Project” ( Huifu Office Letter [2019] No.
    24)


    .
    The "ExxonMobil Huizhou Chemical Complex Project" in the above documents includes the construction content of this project

    .

            7.
    According to the document No.
    651 of the Development and Reform Office [2019], it
    is agreed in principle that ExxonMobil (Huizhou) Chemical Co.
    , Ltd.
    uses imported crude oil or naphtha as raw materials
    , and the specific variety and quantity of import matters should be reported to the commercial supervisor in accordance with relevant regulations Department to apply
    .

    It is agreed in principle that ExxonMobil (Huizhou) Chemical Co.
    , Ltd.
    uses imported crude oil or naphtha as raw materials

            8.
    If it is necessary to adjust the construction site, construction scale, main construction content and other relevant contents specified in the project approval document, please submit a modification application in writing in a timely manner in accordance with the relevant provisions of the "Administrative Measures for the Approval and Filing of Enterprise Investment Projects".
    Our committee will make a decision on whether to agree to the change according to the specific circumstances of the project

    .

            9.
    Please ask the Huizhou Development and Reform Bureau to instruct ExxonMobil (Huizhou) Chemical Co.
    , Ltd.
    to apply for planning permission, land use, resource utilization, safety production, environmental impact assessment, and equipment in accordance with relevant laws and administrative regulations before the project starts construction.
    Import tax reduction and other related procedures

    .

            10.
    According to the explanatory letter "ExxonMobil (Huizhou) Chemical Co.
    , Ltd.
    Huizhou Chemical Complex Project (Phase I) Project Commencement" issued by the project unit when the project was adjusted from a reserve project to a planned project, the project should be transferred Construction starts within 12 months from the date of planning the project (i.
    e.
    before July 2020)

    .
    In order to strengthen enterprise credit management, the project unit should start construction on schedule.
    If there is a force majeure that prevents the project from starting, please ask ExxonMobil (Huizhou) Chemical Co.
    , Ltd.
    to submit an extension application to our commission 30 working days before the start date

    .

    Guangdong Provincial Development and Reform Commission

    November 7, 2019

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.