    Sinopec News Network reported recently that the Tianjin LNG Phase II receiving station project undertaken by the Fourth Construction Second Engineering Company ushered in the "first inspection" since the start of construction.
    The inspection team of the Tianjin Bohai Center Quality Supervision Station conducted the construction quality of the Fourth Construction Second Engineering Company.
    Give praise
    .

    At present, the civil construction of the Tianjin LNG Phase II Receiving Station project has entered the construction climax stage, and the steel structure and pipeline installation are gradually being carried out
    .


    After receiving the task, the project department of the No.


    During the construction process, the project department found that in the design, the reinforcement of the civil foundation cap was dense, which caused great difficulty in the installation of anchor bolts and seriously affected the work efficiency
    .


    For this reason, the project department has conducted several construction seminars to study how to fix the bolts, how to smoothly insert the bolts into the bearing platform, and how to control the gap and verticality between the anchor bolts


    The inspection team of Tianjin Bohai Center Quality Supervision Station fully affirmed the rigorous and meticulous work attitude of the employees of the Fourth Construction Second Engineering Company, and praised the project department for continuously strengthening hidden danger investigation and rectification, and continuously strengthening quality education and training and technical disclosure.


    The project department of the Fourth Construction Second Engineering Company stated that in the future construction, it will continue to focus on quality management, pay close attention to the process control of safety and quality, and use high-quality construction to ensure that the various indicators of the project are excellent


    (Qu Zhaogui Fu Xinyu)

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.