    On August 27, with the successful placement of the last secondary quenching heat exchanger in the cracking furnace area, it marked the successful conclusion of the hoisting task of the large-scale equipment of the ethylene plant of the Lianyungang Petrochemical Large-scale Equipment Hoisting Project Department


    .


    Since the first lifting of the water stripping tower of the ethylene plant process on November 28, 2019, during the construction period of 9 months, the project department has scientifically organized 2,500 tons of hydraulic lifting, 2,000 tons of crawler cranes, 1,600 tons of crawler cranes, and 650 tons of crawler cranes.
    Cranes, 450-ton crawler cranes, 400-ton crawler cranes, 350-ton crawler cranes and other mechanical vehicles completed the hoisting of 54 pieces of equipment inside and outside the contract safely, efficiently and with high quality, winning high recognition and unanimous praise from all parties


    .


    During the construction process, all the staff always put their work in the first place, and the ethylene rectification tower, the highest tower of 104m in the whole plant, rose from the ground, the 2000-ton crawler crane hoisted the quench water tower for the first time in Lianyungang, and 3 condensers were limited.
    The achievement of the milestones in the installation of the space compressor workshop, the precise positioning of 56 modules of 7 cracking furnaces at high altitude, and the hoisting of a 596-ton cold box by a 1,600-ton crawler crane.
    .
    .
    are all outstanding achievements of all the participants in overcoming difficulties.
    Results, one hoisting, one commitment, the project uses superb hoisting technology, rigorous management system, good teamwork spirit, and obedience to command, tenacious and hard work >


    .


    The project department is committed to creating high-quality projects with the excellent quality of daring to endure hardships and to move forward.
    Everyone works together and cooperates closely to successfully complete all the tasks in the installation, creating powerful conditions for the progress of subsequent installations, and for the company's brand hoisting strength.
    make outstanding contributions


    .


    On August 27, with the successful placement of the last secondary quenching heat exchanger in the cracking furnace area, it marked the successful conclusion of the hoisting task of the large-scale equipment of the ethylene plant of the Lianyungang Petrochemical Large-scale Equipment Hoisting Project Department


    .


    Since the first lifting of the water stripping tower of the ethylene plant process on November 28, 2019, during the construction period of 9 months, the project department has scientifically organized 2,500 tons of hydraulic lifting, 2,000 tons of crawler cranes, 1,600 tons of crawler cranes, and 650 tons of crawler cranes.
    Cranes, 450-ton crawler cranes, 400-ton crawler cranes, 350-ton crawler cranes and other mechanical vehicles completed the hoisting of 54 pieces of equipment inside and outside the contract safely, efficiently and with high quality, winning high recognition and unanimous praise from all parties


    .


    During the construction process, all the staff always put their work in the first place, and the ethylene rectification tower, the highest tower of 104m in the whole plant, rose from the ground, the 2000-ton crawler crane hoisted the quench water tower for the first time in Lianyungang, and 3 condensers were limited.
    The achievement of the milestones in the installation of the space compressor workshop, the precise positioning of 56 modules of 7 cracking furnaces at high altitude, and the hoisting of a 596-ton cold box by a 1,600-ton crawler crane.
    .
    .
    are all outstanding achievements of all the participants in overcoming difficulties.
    Results, one hoisting, one commitment, the project uses superb hoisting technology, rigorous management system, good teamwork spirit, and obedience to command, tenacious and hard work >


    .


    The project department is committed to creating high-quality projects with the excellent quality of daring to endure hardships and to move forward.
    Everyone works together and cooperates closely to successfully complete all the tasks in the installation, creating powerful conditions for the progress of subsequent installations, and for the company's brand hoisting strength.
    make outstanding contributions


    .


    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.