Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On the morning of August 30, the 100MW photovoltaic power station in Huawei Yemutang, Lingling District, Yongzhou City, was officially connected to the grid for power generation
.
Zhang Yan, deputy secretary of the Yongzhou Municipal Party Committee and secretary of the Political and Legal Committee, attended and announced that the power station was officially connected to the grid for power generation, and Jiang Shansheng, chairman of the Yongzhou CPPCC, Tang Ding, former chairman of the CPPCC, Yan Xingde, vice mayor, Lu Bin, vice chairman of the CPPCC, and Wang Xiaobo, secretary general of the CPPCC, attended the meeting
.
Yongzhou light resources are rich, the annual use of power generation more than 1100 hours, is an ideal area for solar power generation, Yongzhou Huawei Lingling District Bridge 100MW photovoltaic power generation project is Yongzhou Municipal Party Committee, Municipal Government and Lingling District Party Committee, District Government key projects, total investment of 1 billion yuan, total installed capacity of 100MW, is the first completed ground photovoltaic power plant project in Yongzhou, and is currently the largest single ground photovoltaic power station
in Hunan Province.
The project is located in the Jieqiao Street Office, mainly making full use of the rocky desertification barren mountains of Jieqiao, and focusing on building Jieqiao into a photovoltaic town and renewable energy demonstration point
.
After the completion of the project, the annual power generation capacity will reach 124.
4 million kilowatts, the annual income will be 120 million yuan, and the tax payment will be more than 20 million yuan, which can save 28,000 tons of standard coal, reduce 996 tons of sulfur dioxide, 364 tons of nitrogen dioxide and 66,000 tons
of carbon dioxide.
Since the start of the photovoltaic power generation project on November 6, 2016, by the end of June 2017, 42% of the total project has been completed, the investment of 420 million yuan has been completed, the first phase of the project has been fully completed, the second phase of the project has been started, it is expected to complete the basic project before the end of December 2017, and officially connect to the grid before
the end of June 2018.
On the morning of August 30, the 100MW photovoltaic power station in Huawei Yemutang, Lingling District, Yongzhou City, was officially connected to the grid for power generation
.
Zhang Yan, deputy secretary of the Yongzhou Municipal Party Committee and secretary of the Political and Legal Committee, attended and announced that the power station was officially connected to the grid for power generation, and Jiang Shansheng, chairman of the Yongzhou CPPCC, Tang Ding, former chairman of the CPPCC, Yan Xingde, vice mayor, Lu Bin, vice chairman of the CPPCC, and Wang Xiaobo, secretary general of the CPPCC, attended the meeting
.
Yongzhou light resources are rich, the annual use of power generation more than 1100 hours, is an ideal area for solar power generation, Yongzhou Huawei Lingling District Bridge 100MW photovoltaic power generation project is Yongzhou Municipal Party Committee, Municipal Government and Lingling District Party Committee, District Government key projects, total investment of 1 billion yuan, total installed capacity of 100MW, is the first completed ground photovoltaic power plant project in Yongzhou, and is currently the largest single ground photovoltaic power station
in Hunan Province.
The project is located in the Jieqiao Street Office, mainly making full use of the rocky desertification barren mountains of Jieqiao, and focusing on building Jieqiao into a photovoltaic town and renewable energy demonstration point
.
After the completion of the project, the annual power generation capacity will reach 124.
4 million kilowatts, the annual income will be 120 million yuan, and the tax payment will be more than 20 million yuan, which can save 28,000 tons of standard coal, reduce 996 tons of sulfur dioxide, 364 tons of nitrogen dioxide and 66,000 tons
of carbon dioxide.
Since the start of the photovoltaic power generation project on November 6, 2016, by the end of June 2017, 42% of the total project has been completed, the investment of 420 million yuan has been completed, the first phase of the project has been fully completed, the second phase of the project has been started, it is expected to complete the basic project before the end of December 2017, and officially connect to the grid before
the end of June 2018.