    Home > Chemicals Industry > New Chemical Materials > The progress of the National Energy Yulin PGA project is 43% completed, and it will be handed over at the end of July

    The progress of the National Energy Yulin PGA project is 43% completed, and it will be handed over at the end of July

    • Last Update: 2022-05-08
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    In the first quarter, National Energy Group Yulin Chemical Co.


    In the first quarter, National Energy Group Yulin Chemical Co.


    Project construction goes hand in hand


    Project construction goes hand in hand



    In addition, it was reported in mid-April that the construction of the 50,000-ton/year polyglycolic acid (PGA) project of Guoneng Yulin Chemical Co.
    , Ltd.
    will start in March 2021
    .
    At the end of June of the same year, due to the suspension of energy consumption indicators, the golden season of civil construction was missed
    .
    Reopening in November
    .
    On November 20, the first large-scale tower equipment methyl glycolate purification tower was successfully hoisted
    .
    In 2022, the refined unit steel structure and 10kV substation, one of the milestone control points, were completed in mid-March
    .
    The civil works are expected to be completed by mid-April
    .
    Equipment installation and piping in the southern area entered the peak construction period
    .
    It is expected that the machinery will be completed by the end of June, and it will be fully completed by the end of July
    .
    In addition, it was reported in mid-April that the construction of the 50,000-ton/year polyglycolic acid (PGA) project of Guoneng Yulin Chemical Co.
    , Ltd.
    will start in March 2021
    .
    At the end of June of the same year, due to the suspension of energy consumption indicators, the golden season of civil construction was missed
    .
    Reopening in November
    .
    On November 20, the first large-scale tower equipment methyl glycolate purification tower was successfully hoisted
    .
    In 2022, the refined unit steel structure and 10kV substation, one of the milestone control points, were completed in mid-March
    .
    The civil works are expected to be completed by mid-April
    .
    Equipment installation and piping in the southern area entered the peak construction period
    .
    It is expected that the machinery will be completed by the end of June, and it will be fully completed by the end of July
    .
    In addition, it was reported in mid-April that the construction of the 50,000-ton/year polyglycolic acid (PGA) project of Guoneng Yulin Chemical Co.
    , Ltd.
    will start in March 2021
    .
    At the end of June of the same year, due to the suspension of energy consumption indicators, the golden season of civil construction was missed
    .
    Reopening in November
    .
    On November 20, the first large-scale tower equipment methyl glycolate purification tower was successfully hoisted
    .
    In 2022, the refined unit steel structure of one of the milestone control points and the 10kV substation have been completed in mid-March
    .
    The civil works are expected to be completed by mid-April
    .
    Equipment installation and piping in the southern area entered the peak construction period
    .
    It is expected that the machinery will be completed by the end of June, and it will be fully completed by the end of July
    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.