Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
In the first quarter, National Energy Group Yulin Chemical Co.
In the first quarter, National Energy Group Yulin Chemical Co.
Project construction goes hand in hand
Project construction goes hand in hand
In addition, it was reported in mid-April that the construction of the 50,000-ton/year polyglycolic acid (PGA) project of Guoneng Yulin Chemical Co.
, Ltd.
will start in March 2021
.
At the end of June of the same year, due to the suspension of energy consumption indicators, the golden season of civil construction was missed
.
Reopening in November
.
On November 20, the first large-scale tower equipment methyl glycolate purification tower was successfully hoisted
.
In 2022, the refined unit steel structure and 10kV substation, one of the milestone control points, were completed in mid-March
.
The civil works are expected to be completed by mid-April
.
Equipment installation and piping in the southern area entered the peak construction period
.
It is expected that the machinery will be completed by the end of June, and it will be fully completed by the end of July
.
In addition, it was reported in mid-April that the construction of the 50,000-ton/year polyglycolic acid (PGA) project of Guoneng Yulin Chemical Co.
, Ltd.
will start in March 2021
.
At the end of June of the same year, due to the suspension of energy consumption indicators, the golden season of civil construction was missed
.
Reopening in November
.
On November 20, the first large-scale tower equipment methyl glycolate purification tower was successfully hoisted
.
In 2022, the refined unit steel structure and 10kV substation, one of the milestone control points, were completed in mid-March
.
The civil works are expected to be completed by mid-April
.
Equipment installation and piping in the southern area entered the peak construction period
.
It is expected that the machinery will be completed by the end of June, and it will be fully completed by the end of July
.
In addition, it was reported in mid-April that the construction of the 50,000-ton/year polyglycolic acid (PGA) project of Guoneng Yulin Chemical Co.
, Ltd.
will start in March 2021
.
At the end of June of the same year, due to the suspension of energy consumption indicators, the golden season of civil construction was missed
.
Reopening in November
.
On November 20, the first large-scale tower equipment methyl glycolate purification tower was successfully hoisted
.
In 2022, the refined unit steel structure of one of the milestone control points and the 10kV substation have been completed in mid-March
.
The civil works are expected to be completed by mid-April
.
Equipment installation and piping in the southern area entered the peak construction period
.
It is expected that the machinery will be completed by the end of June, and it will be fully completed by the end of July
.