    The total investment is 33.9 billion yuan! Jilin Petrochemical Transformation and Upgrading Project started construction of 1.2 million tons of ethylene plant

    • Last Update: 2022-12-04
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    On November 12, Jilin Petrochemical's 1.
    2 million tons/year ethylene plant construction project officially started
    .

    The 1.
    2 million tons/year ethylene plant is the most critical plant of Jilin Petrochemical Refining and Chemical Transformation and Upgrading Project (referred to as "Jihua Transformation and Upgrading Project"), with a construction investment of 3.
    729 billion yuan, with an annual output of 1.
    2 million tons of polymer-grade ethylene and 587,000 tons of polymer-grade propylene, while by-product hydrogen, mixed carbon IV and other products, the ethylene plant covers a total area of 118,600 square meters, using ethylene technology
    of Sinopec Engineering Construction Co.
    , Ltd.
    After completion and operation, the total ethylene production capacity of Jilin Petrochemical will reach 1.
    9 million tons/year, and the ethylene production capacity and chemical scale will reach the domestic advanced level
    .

    Contains acrylonitrile, MMA, etc.
    ! Jihua transformation and upgrading project started

    It is reported that the total investment of Jihua transformation and upgrading project is 33.
    9 billion yuan, and 21 sets of refining and chemical plants such as 1.
    2 million tons/year ethylene and 600,000 tons/year ABS will be built, which is the first large-scale petrochemical project
    approved by the state since the "14th Five-Year Plan".
    These projects are arranged in the eastern, central and western regions, and were fully launched
    on February 8 this year.

    On September 25, the first batch of infrastructure design approval projects in the western region of the Jihua Transformation and Upgrading Project started construction, marking that the Jihua Transformation and Upgrading Project officially entered the construction stage
    .

    Western Region of the current project:

    The western area of the Jihua transformation and upgrading project covers a total area of 479,000 square meters, and focuses on key chemical plants such as acrylonitrile, styrene, ABS, etc.
    , as well as 300,000 tons/year of synthetic ammonia and 250,000 tons/year of MMA plants
    .
    At present, acrylonitrile, methyl ester plants and other projects have full start conditions
    .
    The acrylonitrile plant is also the first project to start construction among the 21 new plants in the Jihua Transformation and Upgrading Project
    .

    At present, pile foundation construction is underway in the western region, and it is planned that by March next year, more than 60% of the pile foundation and underground water supply and drainage pipelines will be completed, creating conditions for the next step of overall civil and steel structure construction, and it is expected to complete CCCC
    in 2024.

    The western regional construction project is ethylene downstream products, but also the production raw material of Jilin chemical fiber related products, and can be put into production
    in advance after the completion of the project.
    At that time, the production capacity of ABS, acrylonitrile and methyl ester of Jilin Petrochemical's advantageous chemical products can achieve domestic leadership, especially the annual production capacity of ABS will reach 1.
    8 million tons, accounting for about 60% of the domestic market share, ranking first
    in the country.
    In addition, Jilin Petrochemical will also add new products suitable for automotive, medical, food, alloy modification and other application fields, optimize the product structure, and improve
    the market competitive advantage.

    By the end of September, the basic design of 16 tender sections with the 1.
    2 million tons/year ethylene plant as the core was fully launched, the procurement of 29 technical process packages was completed, the overall design was approved, the long-term equipment procurement had been started, and the overall project was progressing smoothly
    .

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.