    The Yushen 200MWp photovoltaic power generation project of Yellow River Company was officially connected to the grid for power generation

    • Last Update: 2022-11-23
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    At 14:08 on December 31, amid the deafening sound of firecrackers, the first batch of units of the Yushen 200MWP photovoltaic power generation project of Yellow River Company were officially connected to the grid for power generation, laying the foundation
    for the project to be fully connected to the grid next year.

    Yushen 200MWp photovoltaic power generation project was approved by the Shaanxi Provincial Development and Reform Commission in 2013 and started construction
    in April 2016.
    Affected by the national forestry policy, construction
    was suspended in May 2016.
    In order to promote the progress of the project, the company actively worked hard and fully communicated with the Forestry Department of Shaanxi Province, Yulin Forestry Bureau and Yushen Management Committee for many times, and finally made a breakthrough in the name of "Inefficient Shrub Forest Transformation Forest Light Complementary Demonstration Project" and resumed work
    in August 2016.
    The smooth implementation of this project has broken the bottleneck restricting the development of new energy projects in northern Shaanxi and laid the foundation
    for the company's future development in Shaanxi.

    In order to ensure the smooth progress of this grid-connected work, all the company's employees and related construction participants went all out after 58 hours of continuous struggle, and the 330kV Mohai substation started trial operation at 7:18 on December 31 and completed
    successfully.

    At 14:08 on December 31, amid the deafening sound of firecrackers, the first batch of units of the Yushen 200MWP photovoltaic power generation project of Yellow River Company were officially connected to the grid for power generation, laying the foundation
    for the project to be fully connected to the grid next year.

    photovoltaic

    Yushen 200MWp photovoltaic power generation project was approved by the Shaanxi Provincial Development and Reform Commission in 2013 and started construction
    in April 2016.
    Affected by the national forestry policy, construction
    was suspended in May 2016.
    In order to promote the progress of the project, the company actively worked hard and fully communicated with the Forestry Department of Shaanxi Province, Yulin Forestry Bureau and Yushen Management Committee for many times, and finally made a breakthrough in the name of "Inefficient Shrub Forest Transformation Forest Light Complementary Demonstration Project" and resumed work
    in August 2016.
    The smooth implementation of this project has broken the bottleneck restricting the development of new energy projects in northern Shaanxi and laid the foundation
    for the company's future development in Shaanxi.

    In order to ensure the smooth progress of this grid-connected work, all the company's employees and related construction participants went all out after 58 hours of continuous struggle, and the 330kV Mohai substation started trial operation at 7:18 on December 31 and completed
    successfully.

    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.