Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network reported on July 4, in order to regain the time lost due to the delayed arrival of C-301 large-scale propylene oxide equipment at Tianjin Petrochemical, the professional project department of the Fourth Construction Special Operations Engineering Company established a special hoisting team to organize carefully and plan rationally.
, Through the efforts of all the staff involved in the construction, the task of lifting large equipment is completed safely and smoothly
.
The large-scale equipment of Tianjin Petrochemical's propylene oxide project has a net weight of 49 tons and a lifting weight of 70 tons.
The total load of the main crane is 93 tons during lifting.
A 450-ton crawler crane and a 200-ton crawler crane are used for the lifting.
The bit radius reaches 16 meters
.
The hoisting team of the Fourth Construction Special Operation Engineering Company coordinated and deployed, and interchanged the 450-ton crawler crane and the 200-ton crawler crane in a limited site to ensure the best lifting station
.
Before hoisting, the project team eliminated all hidden safety hazards, and checked carefully and confirmed the hoisting conditions one by one
At 2:18 pm that day, with the commander-in-chief's clear whistle, the hoisting work officially began
.
During the hoisting process, the party members of the project department Xianfeng Post and the Youth Assault Team were able to “stand, rush, withstand, and win” at critical moments.
The construction team of the Fourth Construction Special Operations Engineering Company stated that in the follow-up construction, it will continue to carry forward the work >
(Qu Zhaogui Liu Pan)