    On April 16, 2021, the 2# 1.
    4 million ton/year ethylene plant of Zhejiang Petrochemical Co.
    , Ltd.
    's 40 million tons/year refining and chemical integration project phase II project, which was contracted by Wison Engineering, successfully produced qualified ethylene products, and the plant was stable Run, the project is a success in one drive!

    On April 16, 2021, the 2# 1.
    4 million ton/year ethylene plant of Zhejiang Petrochemical Co.
    , Ltd.
    's 40 million tons/year refining and chemical integration project phase II project, which was contracted by Wison Engineering, successfully produced qualified ethylene products, and the plant was stable Run, the project is a success in one drive!

    On April 16, 2021, the 2# 1.
    4 million ton/year ethylene plant of Zhejiang Petrochemical Co.
    , Ltd.
    's 40 million tons/year refining and chemical integration project phase II project, which was contracted by Wison Engineering, successfully produced qualified ethylene products, and the plant was stable Run, the project is a success in one drive!

    Zhejiang Petrochemical Phase II 2# 1.
    4 million ton ethylene plant uses raw materials such as ethane, butane, light naphtha, aromatic raffinate, hydrotreating oil, hydrocoking naphtha, hydrocracking tail oil, etc.
    Using Technip's pre-depropanization and pre-hydrogenation technology, the main products are polymer-grade ethylene and polymer-grade propylene; the main by-products are hydrogen, cracked carbon 4, crude pyrolysis gasoline, light/heavy fuel oil,


    etc.


    Zhejiang Petrochemical Phase II 2# 1.
    4 million ton ethylene plant uses raw materials such as ethane, butane, light naphtha, aromatic raffinate, hydrotreating oil, hydrocoking naphtha, hydrocracking tail oil, etc.
    Using Technip's pre-depropanization and pre-hydrogenation technology, the main products are polymer-grade ethylene and polymer-grade propylene; the main by-products are hydrogen, cracked carbon 4, crude pyrolysis gasoline, light/heavy fuel oil,

    etc.
    The 2# 1.
    4 million ton ethylene plant is a key component of the second phase of the Zhejiang Petrochemical Refining and Chemical Integration Project, one of the largest refining and chemical integration projects in the world

    .
    The civil construction of the project started on April 3, 2019.
    By September 30, 2020, it will meet the conditions for mid-term delivery, and it took only 17 months; on January 31, 2021, the cracking furnace was completed; on April 16, 2021, The 2# 1.
    4 million tons/year ethylene plant was put into operation at one time and successfully started up!
    In the process of project construction, Wison has always adhered to the values ​​of "customer respect and integrity-based", overcoming unfavorable factors such as limited construction period and sudden epidemic situation, and building "zero defect in quality, zero harm in safety, and zero pollution in the environment" A total of 11 million safe working hours have been achieved without casualties
    .
    Wison Engineering relies on the global procurement strength accumulated in international projects over the years, with rich project management experience in the ethylene field and excellent talent team, with a 100% pass rate for material procurement, 100% pass rate for unit projects, and 100% for welding.
    The first-time pass rate of 98.
    34% achieved high standards and high-quality delivery on schedule, which once again proved Wison Engineering's comprehensive strength in general contracting for super-large ethylene plants

    .
    Zhejiang Petrochemical Phase II 2# 1.
    4 million ton ethylene plant uses raw materials such as ethane, butane, light naphtha, aromatic raffinate, hydrotreating oil, hydrocoking naphtha, hydrocracking tail oil, etc.
    Using Technip's pre-depropanization and pre-hydrogenation technology, the main products are polymer-grade ethylene and polymer-grade propylene; the main by-products are hydrogen, cracked carbon 4, crude pyrolysis gasoline, light/heavy fuel oil,

    etc.
    The 2# 1.
    4 million ton ethylene plant is a key component of the second phase of the Zhejiang Petrochemical Refining and Chemical Integration Project, one of the largest refining and chemical integration projects in the world

    .
    The civil construction of the project started on April 3, 2019.
    By September 30, 2020, it will meet the conditions for mid-term delivery, and it took only 17 months; on January 31, 2021, the cracking furnace was completed; on April 16, 2021, The 2# 1.
    4 million tons/year ethylene plant was put into operation at one time and successfully started up!
    In the process of project construction, Wison has always adhered to the values ​​of "customer respect and integrity-based", overcoming unfavorable factors such as limited construction period and sudden epidemic situation, and building "zero defect in quality, zero harm in safety, and zero pollution in the environment" A total of 11 million safe working hours have been achieved without casualties
    .
    Wison Engineering relies on the global procurement strength accumulated in international projects over the years, with rich project management experience in the ethylene field and excellent talent team, with a 100% pass rate for material procurement, 100% pass rate for unit projects, and 100% for welding.
    The first-time pass rate of 98.
    34% achieved high standards and high-quality delivery on schedule, which once again proved Wison Engineering's comprehensive strength in general contracting for super-large ethylene plants

    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.