Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
- Cosmetic Ingredient
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
China Petrochemical News Network reported on August 26 that it was learned from the Zhongke Refining and Chemical Project that as the delivery date for the installation of 120,000 cubic meters of low-temperature propane tanks for liquid hydrocarbon projects and 6 storage tanks for marine fuel oil storage facilities is approaching, the petrochemical four The construction project management team Zhongke Refining & Chemical Co.
, Ltd.
pays close attention to the installation quality of storage tanks, creating conditions for the project to be delivered and put into use on schedule
.
According to reports, the low-temperature propane tank of the Zhongke Refinery Liquid Hydrocarbon Project has a design capacity of 120,000 cubic meters, of which: the diameter of the outer tank is 74 meters, the diameter of the inner tank is 72 meters, the main structure of the tank dome is 46.
5 meters high, and the inner tank is about 34.
1 high.
Meters, a total of 10 rings of wall panels are welded together; the tank area of the newly built marine fuel oil storage facility mainly includes 4 sets of 20,000 cubic meter storage tanks and 2 sets of 10,000 cubic meter storage tanks, each of which is composed of 9 rings of wall Welded plates, including: 20,000 cubic meters of storage tank, inner diameter of 20 meters, 23 meters high, 10,000 cubic meters of storage tank, inner diameter of 15 meters, height of 21 meters
.
In order to ensure the delivery of low-temperature propane tanks for the liquid hydrocarbon project of Zhongke Refinery and large-scale storage tanks for newly-built marine fuel oil storage facilities on schedule, the project management team of the fourth construction project of the petrochemical company Zhongke Refinery on behalf of the owner's project management department focuses on quality control.
, A lot of work has been done closely around the key processes such as prefabrication of tank wall panels and panel assembly butt welding
.
The prefabricated materials of storage tanks should be carefully reported for inspection, especially to ensure that the storage tanks are not deformed during the welding process.
Up to now, the 10th circle of the inner tank siding of 120,000 cubic meters of low-temperature propane tanks has been installed 30%, the new marine fuel oil project has completed two 10,000 cubic meters of storage tanks, and two 20,000 cubic meters of storage tanks are in progress.
(Qu Zhaogui Meng Xiangshan Yu Xin)