    15 conditions are indispensable!

    • Last Update: 2021-06-08
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com

    Global Coatings Network News: On March 18, the Inner Mongolia Autonomous Region Department of Industry and Information Technology issued a letter on soliciting opinions on the "Inner Mongolia Autonomous Region Chemical Industry Park (Chemical Concentration Area) Certification Management Measures (Trial) (Draft for Solicitation of Comments)".

    The draft for comments proposed that the identified chemical park should meet 15 conditions.
    According to the "Inner Mongolia Autonomous Region Chemical Park Evaluation Index System", the park's planning layout, infrastructure, safety production, environmental protection, green development, industrial economy, and integration of industrialization and industrialization A detailed evaluation was carried out in various aspects, and it was determined that the total score of the park should be 60 points and above.
    For those who do not meet the qualification requirements, they will be recognized in accordance with the procedures after the completion of the rectification within one year; those who cannot complete the rectification shall not be recognized.
    No new construction, reconstruction or expansion of chemical projects shall be allowed outside the recognized chemical parks.



    A follow-up evaluation is carried out for the identified chemical parks every three years, and those that do not meet the certification conditions should be rectified within a time limit; if the rectifications do not meet the certification conditions after the deadline, the certification of the chemical parks will be cancelled.


    Existing hazardous chemical production and storage enterprises outside the chemical park shall gradually move into the chemical park in accordance with the industrial layout and policies of the state and autonomous region.
    For chemical parks where major or above production safety accidents or environmental emergencies occur, the procedures for new and expanded projects other than the remediation of safety hazards and environmental pollution control projects shall be suspended within one year.




    The recognized chemical park shall meet the following conditions:

    The recognized chemical park shall meet the following conditions:


    (1) Comply with the "Safety Production Law of the People's Republic of China", "Hazardous Chemicals Safety Management Regulations" and other laws, regulations and regulations, and "Chemical Park Safety Risk Inspection and Governance Guidelines (Trial)" and other related regulations.



    (2) The industrial development direction is in line with the industrial layout positioning of the development zone and the industrial planning layout of the development zone determined by the relevant national and autonomous regional plans and plans, and the industrial positioning is clear, highly relevant, and has a relatively complete scale industrial chain or characteristic industrial chain .


    A relatively complete public infrastructure meeting the planning of the chemical park has been built.




    (3) The chemical park has been approved by the national and autonomous regional people's governments at all levels to establish a clear management organization; it has a clear area and four-dimensional range, and the land within the four-dimensional range conforms to the national land and space plan.



    (4) The chemical park should establish a management organization with clear responsibilities, appropriate powers and responsibilities, and a clear subject, with effective management capabilities in safety production, environmental protection, and emergency rescue.


    The number and scale of safety, ecological and environmental protection supervision and law enforcement personnel are matched with the number and scale of enterprises in the park, and they have effective management capabilities such as safety, environmental protection and emergency.




    (5) The chemical park complies with the national land and space plan, and is connected with the local regional overall plan, ecological environment protection plan, safety production, and comprehensive disaster reduction and prevention plans.


    An industrial plan has been prepared to clarify the positioning of the chemical industry and the leading industrial chain for key development.
    The industrial plan has been verified by experts.
    It has an overall safety risk assessment and planning environmental impact assessment report that has been approved or reviewed and is within the validity period.




    (6) By the end of 2020, there will be no less than 3 chemical production enterprises or more than 30% of the output value, or more than 3 billion yuan in output value.



    (7) The distance between the production and storage devices of the chemical park enterprise and the surrounding schools, hospitals, commercial centers, residential areas and other sensitive points meets the relevant requirements of safety and atmospheric environmental protection; the external safety and health protection distance of the hazardous chemical enterprise meets the requirements; the park; Domestic hazardous chemical companies have realized closed management.



    (8) The functional zoning, general layout, layout of production and storage devices and infrastructure supporting facilities in the chemical park shall comply with relevant standards and specifications to ensure safety and environmental capacity, effectively reduce regional risks, and prevent chain accidents.


    There are no labor-intensive non-chemical companies and food industries and other light industries in the park.




    (9) The park establishes risk classification for the safety management of hazardous chemical processes involved in key supervision, hazardous chemicals under key supervision and major hazards ("two key points and one major"), explosive chemicals and precursor chemicals The management and control and hidden danger investigation system, involving "two key points and one major" production and storage devices, shall be equipped with flammable and toxic gas leak detection alarms, emergency shut-off devices and automated control systems in accordance with relevant industry management and design specifications.



    (10) The chemical park should realize closed management, have corresponding checkpoints, guard posts, barriers or similar traffic control and anti-intrusion facilities, and have road high-definition cameras and other facilities that can monitor the trajectory of hazardous chemical transport vehicles.



    (11) The chemical park should establish a complete safety risk monitoring and monitoring system, including but not limited to high-altitude observation video monitoring, video monitoring of key roads and intersections, "two key points and one major" video monitoring, video monitoring of key work sites, and toxic and hazardous gases And flammable gas monitoring and monitoring, etc.



    (12) The chemical park shall establish a safety (environmental protection) emergency management system and system that meets the emergency requirements of production safety (environmental emergencies), prepare emergency plans for production safety accidents (emergency environmental incidents), and conduct drills at least once a year.


    Establish including but not limited to special service fire station, safety (environmental protection) emergency rescue team and equipment, safety (environmental protection) emergency rescue material warehouse, safety (environmental protection) emergency rescue expert database, safety (environmental protection) emergency rescue command center, emergency rescue medical center Wait.








    (15) The chemical park and the enterprises in the park shall have the supporting capabilities for 100% collection and 100% safe treatment and disposal of the hazardous waste generated, and comply with relevant regulations.





    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.