    Dalian Zhuanghe offshore wind power project wind turbine lifting was successfully completed

    • Last Update: 2020-11-25
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    On November 12, at the construction site of the 65th machine of Dalian Zhuanghe Project, with the last blade rising slowly, Longyuan Zhenhua Project Department completed the last typhoon lifting of the Three Gorges New Energy Dalian Zhuanghe Offshore Wind Power Project.
    The project is located in the Zhuanghe Sea of Dalian City, Liaoning Province, with two units with a capacity of 3 MW, 50 units with a capacity of 3.3 MW and 21 units with a capacity of 6.45 MW, with a installed capacity of 300 MW.
    wind farm supporting the construction of a 220 kV sea rising pressure station and an on-land central control center.
    Zhenhua is responsible for the installation of three 3.3 MW wind turbines and 14 6.45 MW wind turbines for the project.
    Dalian Zhuang River project sea area average depth of 15 meters, more than 20 nautical miles offshore, in the unsealed sea, wind and waves, coupled with the silt of the underwater beach, increased the difficulty of construction.
    project area is located in the northern Yellow Sea, the winter cold needs to implement the "winter break", can be operating days less.
    Faced with heavy tasks, tight construction time, poor environment of the construction sea conditions, Longyuan Zhenhua Project Department in practice groped out a set of deep-water surge construction shaft, and actively explore process optimization measures, and finally successfully single-machine capacity of 6.45 MW wind turbine lifting construction work from the original 110 hours stable to about 87 hours, to achieve the lifting completed fan synchronous completion of site acceptance, 4 days to complete the unit project acceptance.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.