    Ningxia Kunpeng coal-to-ethylene glycol project transferred to equipment installation in July

    • Last Update: 2022-02-16
    • Source: Internet
    • Author: User
    Search more information of high quality chemicals, good prices and reliable suppliers, visit www.echemi.com
    On the morning of June 18th, Cui Bo, chairman of the CPPCC of Ningxia Autonomous Region, and his party came to the site of the ethylene glycol project of Ningxia Kunpeng Clean Energy Co.
    , Ltd.
    to conduct on-site inspections on the construction and development of the project
    .
    At the ethylene glycol project site, Dang Yanping, chairman of Ningxia Baoli Group, reported in detail the overall planning and project construction of the ethylene glycol project
    .
    The 400,000-ton/year coal-to-ethylene glycol project of Ningxia Kunpeng Clean Energy Co.
    , Ltd.
    has started construction in March 2019.
    The project has been progressing smoothly.
    The ground pipe construction has been completed, and the civil engineering has been completed 80%.
    It is expected to be transferred in July 2020.
    Enter the stage of comprehensive equipment installation to ensure that it is put into production in accordance with the original schedule
    .
    After listening to the report, Cui Bo highly affirmed the construction and development of the ethylene glycol project
    .
    Companies are required to strictly follow various epidemic prevention and control measures, do a good job in epidemic prevention and control, ensure safe production and the smooth development of project construction, and ensure that projects under construction are put into operation on schedule
    .
    Ningxia Kunpeng Clean Energy Co.
    , Ltd.
    's 400,000 tons of coal-to-ethylene glycol project is one of the key projects of Ningdong Energy and Chemical Base.
    The project is located in the New Chemical Materials Park of Ningdong Base.
    The total investment of the project is 4.
    33 billion yuan.
    Coal is used as raw material for production.
    Syngas is used as raw material to produce ethylene glycol, co-alcohol, hydrogen and other products.
    The main construction content includes gasification, conversion and heat recovery, low-temperature methanol washing, PSA hydrogen production, CO cryogenic separation, co-alcohol plant, 10 sets of main production equipment for sulfur recovery and ethylene glycol, supporting the construction of public and auxiliary facilities such as circulating water field, sewage treatment station, tank farm, loading and unloading, and torch
    .
    The whole process is planned to be completed on June 30, 2021
    .
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.