    First, the underground garage epoxy flooring
    the project basement garage and ramp epoxy flooring construction area of about 41,000 m2. The main content of the work for the ground clean-up, ground chisel, gravel laying, non-woven laying, layer construction, epoxy layer construction, above-ground traffic lines, column zoning lines, parking tags, traffic signs, parking lot numbers.
    . Technical bottoming for workers before starting work
    . Laser leveling machine to the scene
    filter water layer gravel, non-woven fabric, rebar mesh strapping and laying
    . Concrete collapse test before pouring
    concrete pouring
    concrete flatness
    : Basement garage epoxy resin model
    attached: basement epoxy floor paint ground construction process description
    First, construction conditions
    1.1 ambient temperature is not less than 5 degrees C, the best ambient temperature 10-25 degrees C .
    1.2 the ground has passed its maintenance period and contains less than 10% water.
    1.3 The ground should have a flatness that meets the acceptance criteria.
    1.4 the ground shall not have empty drums, large areas of sand and other phenomena.
    II, process flow
    grass-roots treatment→bed coating→ medium coating → batch soil layer →-face coating
    iii, construction methods and process requirements
    3.1 grass-roots treatment
    3.1.1 subsurgency maintenance for more than 28 days, water needs less than 8%, plain uneven or empty drum needs to be removed.
    3.1.2 to level the ground with epoxy mortar.
    3.1.3 oil contamination needs to be thoroughly cleaned.
    3.1.4 Keep the construction site dry and clean before construction.
    3.2 bottom coating
    3.2.1 Need to be kept clean before construction, if there is adhesion to remove, the main agent and hardener proportional mix, fully stirred.
    3.2.2 Adjust the appropriate viscosity depending on the ground conditions, and the mixture needs to be completed within 4 hours.
    3.2.3 bottom coating maintenance hardening time of about 8 hours.
    3.3 medium coating
    3.3.1 need to be kept clean before construction, if there is clutter adhesion needs to be removed, the main agent and hardener proportional mixing, fully stirred.
    3.3.2 mixture is added to quartz sand in moderity.
    3.3.3the material evenly with a knife.
    3.3.4 mix takes 30 minutes to complete.
    3.3.5 Construction junction to do a good job of handover processing.
    has been hardened for approximately 8 hours in 3.3.6.
    3.4 batch soil layer
    3.4.1 need to be kept clean before construction, if there is debris adhesion needs to be removed, the main agent and hardener proportional mix, fully stirred.
    3.4.2 Use a batch knife to coat the material evenly.
    3.4.3 Mix takes 30 minutes to complete.
    3.4.4 batch soil conservation hardening time of about 8 hours.
    3.4.5 according to the actual needs of the construction of several requirements to achieve a flat hole-free, no batch of knife printing and sanding printing.
    3.5-sided coating
    3.5.1 Need to be kept clean before construction, if there is debris adhesion needs to be removed, the main agent and hardener proportionally mixed, fully stirred.
    3.5.2 Using a rollerknife to evenly coat the material, the mixture takes 30 minutes to complete.
    3.5.3 Construction junctions need to be handled.
    3.5.4 construction completed 24h before the person, 72h before the pressure.
    , the quality standard
    4.1 ambient temperature is 25 degrees C, after construction 2-3d should reach the hard work, that is, the hardness reached about 80% of the completion of curing.
    4.2 leveling is good,knife marks, large area interface is basically flat.
    4.3 no floating hair flowers, uniform color, large area interface allows for a very non-obvious color difference.
    4.4 is free of coarse impurities, but allows for minimal defects caused by dust falling in the air.
    4.5 floor surface should be smooth, gloss should meet the design requirements (high gloss ≥90, light ≥70, half light 50 to 70), flat coating type for light, water for half light to no light.
    4.6 orange peel, mortar non-slip surface effect should be obvious.
    2nd, underground garage Gold Sands Floor
    The basement of this project is two floors, functioning for parking and equipment rooms, the second floor underground has a human defense basement.
    . Technical bottoming of workers before starting work
    . Ground chiseling and cleaning of the original structure
    measurement and release line before starting work
    Protection of finished products before floor construction
    Keeping the ground moist and clear before pouring Water
    . . .


    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Looking for slope floor)
    . Laser leveling machine leveling - underground layer (no slope floor)


    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Seam
    . Sprinkler cover film maintenance for 7 days
    attached: King Kong sand flooring construction process description
    First, the introduction of gold sand flooring
    Mainly composed of high-strength cement, inorgent wear-resistant bone, pigment powder (cement primary color no), additives and so on. The aggregate is sandy, with an average particle size of 1.5mm, accounting for about 60% of the total, and the glue is treated with high-label cement, which has a variety of colors to choose from, such as red, yellow, green and gray. Hardener bone composition is natural ore. Non-metallic bone that is not rusty and has a hardness of more than 8 degrees Mohs. In addition to natural ore materials, other cement, color materials and other weight does not exceed 25% of the total weight. This product is directly constructed on the concrete or cement mortar surface in the initial condensation stage, and after being flattened, a hard, hard-drying, dust-free and beautiful hardened floor is formed.
    The essence of the gold sand floor is also cement products, it is a high-grade cement and different levels of quartz sand mixed products, it certainly has the characteristics of cement products: free state ca, Mg , from the pores non-stop predate the production of dust; By hydration cooperation with the loss of water at the end, resulting in a lot of capillary holes, and thus caused by non-dense, so its strength, wear resistance are greatly reduced, because the thickness of the diamond sand is generally 3 to 5 mm, very easy to fall off, if the time of the material is not well mastered. After the thickness of this layer is worn, the cement below begins to ash, so usually after one year of use of the floor, even if there is wax maintenance, it is inevitable scratching and wear.
    II, the performance characteristics and scope of application
    The color of the gold sand floor is optional, the surface is dense, not easy to dust, easy to clean, is a replacement for traditional industrial ground hydration grinding stone. Products are low cost-effective, cost-effective, long service life, wear resistance, impact resistance, pressure resistance performance is excellent. The construction is simple and is directly soused on the primary concrete, saving time and labor, eliminating the need for the construction of mortar surfaces, high wear resistance, reduced dusting, improved impact resistance, and improved oil and grease resistance.
    The scope of application of the gold sand floor: because the performance of epoxy flooring and gold sand flooring is not the same, so in use must be based on the environment and needs to choose, epoxy flooring is applicable in no particularly frequent vehicle walking, no heavy objects often impact, no sharp hard objects often friction, no strong corrosive chemicals exist in a variety of industrial, civil, commercial flooring. And the sand wear-resistant flooring is suitable for all kinds of industrial, civil and commercial flooring that need to withstand frequent vehicle walking, frequent heavy impact, often sharp hardening friction, non-corrosive chemical presence, low requirements for cleanliness, and low aesthetic requirements.
    , the construction process
    bed concrete control→ the first stage of material scattering construction→ erasing→ lighting→ maintenance→ cutting seams, fillers.
    1. Concrete substation to find a flat layer requires thickness of 30mm-50mmM or more, strength of C25 or more, minimum gel material content, site collapse degree of 75-100mm, the surface should be dense, flat, and no water.
    2. When concrete first condenses, it is tested with finger pressure, leaving a 3-5MM imprint, and construction can begin.
    3. Hand-cast ground hardening material, until its absorption of concrete moisture wet can be used to wipe the press to solidize, collect light.
    4. Use a hand-smear knife to light up the mechanical construction area.
    . During the construction process, do not throw water on the surface.
    6. After the completion of the surface with special maintenance agents, with fine fog-like spray construction maintenance, do not cover with plastic cloth.
    7. Cut the telescopic seam.
    8. Use sealed coatings.
    9. Sealing coatings: In some cases, there are high requirements for aesthetics and chemical corrosion resistance, at this time it is recommended to cover a layer with closed paint.
    This article is an English version of an article which is originally in the Chinese language on echemi.com and is provided for information purposes only. This website makes no representation or warranty of any kind, either expressed or implied, as to the accuracy, completeness ownership or reliability of the article or any translations thereof. If you have any concerns or complaints relating to the article, please send an email, providing a detailed description of the concern or complaint, to service@echemi.com. A staff member will contact you within 5 working days. Once verified, infringing content will be removed immediately.

    Contact Us

    The source of this page with content of products and services is from Internet, which doesn't represent ECHEMI's opinion. If you have any queries, please write to service@echemi.com. It will be replied within 5 days.

    Moreover, if you find any instances of plagiarism from the page, please send email to service@echemi.com with relevant evidence.